OMV Petrom Secures NPRR Funding for Green Hydrogen Production in Romania

Key highlights
  • The financing contract is worth up to EUR 39 million, with a total investment estimated at EUR 74 million.
  • The project will establish a 20 MW hydrogen production capacity at the Petrobrazi refinery.
  • The hydrogen production will generate over 2,600 tons of green hydrogen annually, reducing CO2 emissions by 70%.
  • The final investment decision is expected in 2024, with project completion in 2025.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
OMV Petrom Petrobrazi 55 MW Green Hydrogen Units · Romania
Under Construction
2022
2024
2025
2025
—
Operational / Completed · expected date for subscribers

Project Overview

OMV Petrom has signed a financing contract through the National Plan for Recovery and Resilience to construct a hydrogen production facility at the Petrobrazi refinery in Romania. The contract, signed with the Ministry of Energy, is valued at up to EUR 39 million, with the total investment estimated at EUR 74 million.

Hydrogen Production Capacity

The project will establish a 20 MW hydrogen production capacity using water electrolysis, powered entirely by renewable energy. This process will ensure that no CO2 emissions are generated during the separation of oxygen and hydrogen molecules.

Environmental Impact

The facility is expected to produce over 2,600 tons of green hydrogen annually. The integration of this green hydrogen will lead to a reduction of at least 70% in CO2 emissions across the entire production value chain of sustainable fuels compared to conventional fuels.

Timeline and Next Steps

OMV Petrom will initiate a public tender for the purchase of the electrolyzer in the near future. The final investment decision is anticipated in 2024, with the completion of the project expected by 2025.

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

29 September 2026
OMV Petrom advances Strategy 2030 execution

Half of €11bn capex deployed; Neptun Deep first gas H1 2027; renewables, storage, SAF/HVO unit and expanded EV charging to 2030.

21 September 2026
OMV Petrom advances EUR 560m SAF/HVO unit at Petrobrazi

EUR 560m unit to produce 250,000 t/yr SAF and renewable diesel from vegetable fats and used cooking oils; commissioning targeted for 2028.

28 August 2026
OMV Petrom raises Petrobrazi green hydrogen capacity to 55 MW with second 35 MW electrolyzer

Second 35 MW electrolyzer fully delivered, lifting Petrobrazi’s green H2 capacity to 55 MW to supply refining and a 250,000 t/y SAF/HVO unit.

31 July 2026
OMV Petrom Group H1 2026 results

Clean CCS Operating Result 3 bn lei; net income 1.8 bn lei; CAPEX 3.7 bn lei; contribution to state budget 10.2 bn lei; Neptun Deep on track for first gas in 2027.

25 June 2026
OMV Petrom: all modules delivered for 20 MW Petrobrazi electrolyzer

Final module delivered for the 20 MW electrolyzer; it will produce ~3,000 t/yr green hydrogen for the SAF/HVO unit; total planned capacity is 55 MW across two projects.