Jacobs to Conduct Engineering Study for Borealis Plant in Belgium

Key highlights
  • Jacobs awarded FEED study for PDH plant in Kallo, Belgium.
  • New PDH plant targets 740 kilotons annual production capacity.
  • FEED phase completion scheduled for mid-2018.
  • Study includes both inside and outside battery limit areas.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Borealis Kallo PDH2 Propylene Plant · Belgium
Commissioning & Start-up
2016-09
2017-10
2018-10
2019-09
~2025
~2026 Q4

Project Overview

Jacobs Engineering Group Inc. has been awarded a contract to complete a front end engineering design (FEED) study for a propane dehydrogenation (PDH) plant at Borealis' production site in Kallo, Belgium. This follows the successful completion of the feasibility study for the plant.

Production Capacity

The new PDH plant aims for an annual production capacity of 740 kilotons, positioning it as one of the largest and most efficient facilities globally.

Scope of Work

Jacobs will prepare the basic design package for both the inside battery limit areas and the outside battery limit areas of the new PDH plant. The FEED phase is scheduled for completion by mid-2018.

Strategic Importance

This project represents a significant investment in the European chemical industry, addressing market demand for polypropylene and propylene.

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

3 April 2026
Borealis Kallo PDH2 2025 update

Project surpassed 97% construction and precommissioning in 2025; remaining insulation and commissioning work. Start-up planned for H2 2026.

15 December 2025
Borealis Settles Kallo PDH2 Dispute

Borealis and IREM Group settle contract dispute, ending arbitration and allowing both parties to proceed.

18 June 2025
Borealis PDH2 Project Update: Kallo, Belgium

The project is 90% complete, with full mechanical completion in 2025. Start-up is set for Q2 2026. Social compliance measures are ongoing.

30 October 2026
Zhejiang Petroleum & Chemical's 1.2 Mt/yr CATOFIN PDH and the polypropylene outlook

A 1.2 Mt/yr PDH using Lummus CATOFIN highlights why scale, integration and proven technology matter for long-term polypropylene competitiveness despite a current propylene surplus.

10 September 2026
Clariant awarded CATOFIN supply for 1.2 Mtpa PDH unit in China

CATOFIN catalyst and HGM ordered for a 1.2 Mtpa licensed PDH unit in Zhejiang to produce propylene for petrochemical derivatives.