Nordic Ren-Gas Tampere Renewable E-Methane Plant

New construction · Tampere, Finland · FID / Sanctioned

Project of the week

25 November–1 December 2026

Nordic Ren-Gas reached a final investment decision on its Tampere e-methane plant on 20 November, with construction due to begin immediately and completion scheduled for 2029.

The EIB calls it the EU's first e-methane plant financed on a project-finance basis, with lending that rests on the plant's expected revenues. Allianz, Tesi, Japan Hydrogen Fund and Schroders Greencoat provide the equity; the EIB's €60 million loan, about a fifth of the investment of more than €300 million, is the largest of the debt.

This week this project is shown in full: everything a chemXplore subscriber sees on every project.

The project integrates European-sourced technologies into a flexible Power-to-Gas facility that produces RFNBO-compliant e-methane from renewable hydrogen and biogenic CO2 while recovering waste heat for district heating, demonstrating cross-sector coupling to supply heavy-duty transport and maritime sectors.

Where it stands

FID / Sanctioned

The Final Investment Decision has been taken: the owner has committed the capital and the project is approved and funded. This is the pivotal go/no-go milestone that separates speculative projects from committed ones.

  1. Announced / Concept 2022 Source: ren-gas.com
  2. FEED / Pre-FID October 2024 Source: sweco.fi
  3. Under Construction 2026 Q4 (estimated) Source: EIB raises financing framework for Nordic Ren‑Gas to EUR 680m 3 September 2026 · ren-gas.com
  4. Commissioning & Start-up Ahead
  5. Operational / Completed 2029 (estimated) Source: Nordic Ren-Gas takes world’s largest e-methane project to FID 20 November 2026 · Nordic Ren-Gas to build €300m-plus e-methane plant in Tampere 20 November 2026 · ren-gas.com