Petrobras starts Búzios 8 (P-79) production

Key highlights
  • P-79 FPSO entered production three months ahead of the PN 26-30 schedule and five months earlier than PN 25-29.
  • Unit capacity: 180,000 barrels oil per day and 7.2 million m³/d gas compression, lifting Búzios field installed oil capacity to ~1.33 million bpd.
  • Development plan: 14 wells (8 producers, 6 injectors) with intelligent completions and rigid/flexible lines enabling up to 3 million m³/d gas export via the Rota 3 pipeline.
  • Consortium: Petrobras (operator) with partners CNOOC, CNODC and PPSA; P-79 arrived from South Korea and joins other FPSOs while P-80, P-82 and P-83 are under construction and Búzios 12 is in bidding.
Related projects For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Petrobras P-78 and P-79 FPSOs, Búzios Field (Búzios 6 and 8) · Brazil
Operational / Completed
2021-05-10
2025-12-31
2026-05-01
Petrobras FPSO P-83 Búzios Field · Brazil
Under Construction
2022-09
2022-09
2025
Commissioning & Start-up · expected date for subscribers
Operational / Completed · expected date for subscribers

Start of production

On May 1 Petrobras began oil production from the P-79 FPSO (Búzios 8) in the Santos Basin, three months ahead of the PN 26–30 schedule and five months ahead of PN 25–29.

Capacity and exports

P-79 provides 180,000 bpd oil capacity and 7.2 million m³/d gas compression, increasing Búzios installed oil capacity to ~1.33 million bpd and enabling up to 3 million m³/d of gas export via interconnection to the Rota 3 pipeline.

Project layout and technology

The development includes 14 wells (8 producers, 6 injectors) with intelligent completions and will use rigid production, injection and gas export ducts plus flexible service lines; the FPSO has a new-design hull with technologies for emission reduction and operational efficiency, measuring 345 m in length and 180 m in height to the top of the flare.

Logistics, field context and partners

P-79 arrived from South Korea in February with commissioning and operations teams on board, allowing commissioning advances during transit; Búzios—discovered in 2010—is 180 km off Rio de Janeiro in ultra-deep waters (>2,000 m) and hosts multiple FPSOs (P-74, P-75, P-76, P-77, Almirante Barroso, Almirante Tamandaré, P-78), with P-78 entering operation in December 2025, P-80/P-82/P-83 under construction and Búzios 12 in bidding; consortium members include Petrobras (operator), CNOOC, CNODC and PPSA.

Source: Petrobras

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

10 November 2026
Petrobras raises 2026 production and investment projections

Higher output and operating cash generation estimates accompany increased Capex, operating expenses and lease-flow guidance.

3 November 2026
Petrobras P-78 (Búzios 6) Reaches 180,000 barrels per day

Hit nominal capacity; platform 180 km offshore; high permo-porosity, thick reservoir supports strong flows; Búzios will host 12 FPSOs with two due in 2027.

26 August 2026
Búzios field posts new monthly and daily gas export records

July average exports reached 10.8 million m³/d; daily peak hit 14.1 million m³ on 6 August after CO₂-membrane upgrades and Route 3 operation.

6 August 2026
Petrobras posts R$52.4bn Q2 2026 profit

Quarterly results bolstered by record own oil output, above-100% refinery utilization and higher derivative production, supporting cash generation and lower imports.

28 July 2026
Petrobras Q2 2026 own production reaches 3.34 MMboed

Record oil, NGL and gas output reached 3.34 MMboed in Q2, up 14.1% YoY; operated production 4.87 MMboed; refinery utilisation 101.2% and derivative imports at pandemic-low.