Projects Seatrium is involved in

chemXplore tracks 9 projects involving Seatrium, of which 8 are active.

  1. none Announced / Concept
  2. none FEED / Pre-FID
  3. 1 project FID / Sanctioned
  4. 5 projects Under Construction
  5. 2 projects Commissioning & Start-up

Besides these 8, the record holds 1 completed project.

8 more active projects and the 1 that is completed, on hold or cancelled are in the record. See all 9 in chemXplore

Expected start-up, by year
0 1 2 3 2026 2027 2028 2029 2030 2031

The dates themselves, per project, are for subscribers.

Seatrium in chemical industry news

10 November 2026
Petrobras raises 2026 production and investment projections

Higher output and operating cash generation estimates accompany increased Capex, operating expenses and lease-flow guidance.

10 November 2026
Petrobras posts R$39.8bn net profit in Q3 2026

Profit excluding one-off events reached R$47.9bn, up 68% year on year; operating cash flow rose 15% to R$61.8bn.

3 November 2026
Petrobras P-78 (Búzios 6) Reaches 180,000 barrels per day

Hit nominal capacity; platform 180 km offshore; high permo-porosity, thick reservoir supports strong flows; Búzios will host 12 FPSOs with two due in 2027.

28 October 2026
Petrobras production hits record 3.512 MMboed in 3Q26

Operational efficiency, FPSO ramp-ups and fewer shutdown losses drove output growth, supported by 12 new wells and refinery and decarbonization advances.

19 October 2026
Petrobras P-82 Platform Begins Voyage to Búzios Field

Left Singapore on 18/10 bound for the Búzios pre-salt field; part of the 80-series of six platforms with nominal 225,000 bpd and 12 million m³ gas compression capacity; start expected next year.

30 September 2026
Petrobras P-80 (Búzios 9) Departs Singapore for Búzios Field

225,000 bbl/d oil capacity and 12 million m³/d gas processing; first of a six-platform series; P-80 and P-82 due to start production in 2027.

27 August 2026
Petrobras and Seatrium baptize P-80 and P-82 at Tuas shipyard

Two pre-salt platforms bound for the Búzios field will sail to Brazil for 2027 start-up; each can produce 225,000 b/d and treat 12 million m³/d of gas.

26 August 2026
Búzios field posts new monthly and daily gas export records

July average exports reached 10.8 million m³/d; daily peak hit 14.1 million m³ on 6 August after CO₂-membrane upgrades and Route 3 operation.

Where its projects are