- The first 18-month report was accepted by BBI JU.
- Construction of the flagship plant is complete.
- Key equipment installation is nearly finished.
- Commissioning will start once COVID-19 restrictions are lifted.
Project Review and Progress
The SWEETWOODS consortium held a productive review meeting in Brussels in early March. External experts assessed the project's progress and confirmed that it is on track.
First 18-Month Report
The periodic report for the first 18 months of the SWEETWOODS project was accepted by the Bio-Based Industries Joint Undertaking (BBI JU). Significant advancements have been made in novel lignin and cellulosic sugars applications during this period.
Construction and Equipment Installation
Construction of the SWEETWOODS flagship plant in Imavere, Estonia, has been completed. The installation of key equipment is nearly finished, marking a significant milestone in the project.
Impact of COVID-19
While the COVID-19 pandemic has caused delays in the delivery of certain equipment and instruments, all preparations are in place to commence commissioning as soon as pandemic-related restrictions are lifted.