HoloSolis raises over €15m for planned solar gigafactory

Key highlights
  • The Series A raised more than €15m, with Crédit Agricole Group, Algebris, Trina Solar and StarCharge joining existing investors.
  • The factory is estimated to cost €1bn and is designed for annual capacity of 5 GW, equivalent to about 10 million panels.
  • Construction is planned to start in 2028, with production scheduled from 2029.
  • HoloSolis has letters of intent for more than 30 GW with prospective customers; these are not firm orders.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Holosolis Solar4EU 5 GW Solar Cell and Module Factory, Hambach · France
Announced / Concept
2023-05
—
—
Under Construction · expected date for subscribers
Commissioning & Start-up · expected date for subscribers
Operational / Completed · expected date for subscribers

Funding and investors

HoloSolis has raised more than €15m in a Series A round and was selected for support from the European Commission’s Innovation Fund. The grant agreement is still being finalised. Identified project funding and support now exceeds €400m, including amounts already secured and support awaiting contracts. New investors are Crédit Agricole Group, through four regional banks, Algebris, Trina Solar and StarCharge. They join Calès Technologies, Forming and Ecolab.

Factory plans

The planned facility in Sarreguemines, in France’s Grand Est region, will manufacture photovoltaic cells and assemble them into modules on one site. It is designed for annual output of 5 GW, or about 10 million panels, and 2,000 direct jobs. Total investment is estimated at €1bn.

Next steps

A further fundraising round is due to open in the coming month to secure capital for construction. HoloSolis also plans to convert letters of intent covering more than 30 GW into contracts; the letters are not firm orders. Series A proceeds will fund pre-construction studies, plans and technical specifications, production-line supplier selection, and qualification of panel prototypes. Construction is planned to begin in 2028, with production from 2029.

Source: InnoEnergy

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

4 November 2026
EU Innovation Fund backs three InnoEnergy portfolio companies

Projects target low‑carbon iron feedstock, a 5 GW European solar cell and module factory, and biogenic CO₂-to-e‑methane systems, advancing to industrial-scale deployment.

21 October 2026
ORLEN-backed Atlas CO₂ storage project in Norway wins €223m EU Innovation Fund grant

EU awards €223m to support Atlas CO₂ transport and storage on the Norwegian Continental Shelf; designed for 6 Mtpa capacity (expandable) with first injection targeted for 2031.

20 October 2026
Molins, Enagás and Linde selected for EU Innovation Fund support for Mosusol‑NetCO₂

Industrial-scale project to capture about 1 million tCO₂/year at a Barcelona cement plant, combining capture, transport infrastructure and oxy‑combustion technologies.