Chandra Asri CA‑EDC project 72% complete, operations aimed for 2027

Key highlights
  • Construction of the Chlor Alkali–EDC facility is 72% complete as of July 2026.
  • Initial investment exceeds USD 800 million, with operational readiness targeted for 2027.
  • Preparations have begun for a Phase II expansion valued at USD 1 billion to boost long‑term production capacity.
  • The project is projected to create about 250 jobs, improve caustic soda supply reliability and reduce import dependence.
Related projects For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Chandra Asri Cilegon CA-EDC Plant · Indonesia
Under Construction
2025-03-04
2025-03-19
Operational / Completed · expected date for subscribers
Chandra Asri Cilegon CA-EDC Phase II Expansion · Indonesia
Announced / Concept
2026-07
2026-07

Project status

PT Chandra Asri Alkali’s Chlor Alkali and Ethylene Dichloride (CA‑EDC) facility has reached 72% construction progress as of July 2026. The initial phase carries an investment value exceeding USD 800 million and is targeting operational readiness in 2027.

Phase II development

The company has begun preparations for a Phase II development of the CA‑EDC facility, with an announced investment value of USD 1 billion intended to strengthen long‑term production capacity.

Economic and market impact

The establishment of the CA‑EDC facility is expected to create around 250 jobs, empower local business actors, enhance the supply reliability of caustic soda across industrial sectors, and reduce Indonesia’s reliance on imports.

Source: chandra-asri.com