Its role EPC
China Chengda Engineering Co., Ltd. is an international engineering, procurement, and construction (EPC) contractor focused on the chemical, petrochemical, and energy sectors. Headquartered in Chengdu, Sichuan Province, China, it operates as a wholly-owned subsidiary of China National Chemical Engineering Group Corporation Ltd. (CNCEC).
The company originated as the No. 8 Design Institute under China’s Ministry of Chemical Industry in 1958 and was formally established in 1988. It delivers full-lifecycle services from feasibility studies and engineering design to EPC turnkey delivery, commissioning, and operation & maintenance. Core competencies include salt chemical processes (soda ash, chlor-alkali, caustic soda, lithium salts), natural gas and coal chemical projects (ammonia, urea, methanol, acetylene derivatives), petrochemical downstream units (PVC, polymers, ethylene derivatives), LNG/LPG terminals, power plants, and municipal infrastructure.
Chengda holds Grade-A comprehensive engineering-EPC qualifications, over 300 national patents, and proprietary technologies, with particular leadership in soda ash and ion-exchange membrane caustic soda processes. It serves major Chinese clients including Sinopec, PetroChina, CNOOC, and Shenhua Group, and has completed more than 40 overseas projects valued cumulatively in billions of USD across more than 20 countries, including Indonesia, Saudi Arabia, the United States, Brazil, Vietnam, Bangladesh, Pakistan, Uzbekistan, and Russia.
With roughly 1,200 employees (over 60% senior professionals), the firm emphasizes digital project delivery, international standards compliance, and technology export. It maintains ISO certifications and has been repeatedly ranked on ENR lists of top international engineering firms.
Also known as China Chengda Engineering.
chemXplore tracks 1 project involving Chengda, of which one is active.
1 more active project is in the record. See all 1 in chemXplore →
USD>800M CA‑EDC plant at 80% completion; main equipment being installed; start planned for 2027; capacities 827 kt caustic soda and 500 kt EDC with significant import substitution and export potential.
Construction of a Chlor‑Alkali and EDC plant is 72% complete; operations targeted for 2027 and Phase II planned with a $1bn investment.
IDR 15 trillion CA-EDC complex with 400kt caustic (solid)/827kt liquid and 500kt EDC yearly; 3,250 jobs; completion targeted for 2027; 2025 capex USD 350–400m.
Designated a National Strategic Project, the CA‑EDC complex will cost IDR 15 trillion and produce 400,000 t caustic soda and 500,000 t EDC per year.
active all projects