Danantara and INA back Chandra Asri CA‑EDC project

Key highlights
  • Strategic investment transaction completed between Danantara Investment Management, Indonesia Investment Authority and Chandra Asri Group.
  • As of September 2026 construction was approximately 80% complete with main equipment being installed and supporting infrastructure under development.
  • Facility designed to produce approximately 400 KTA caustic soda and 500 KTA ethylene dichloride, with commercial operations targeted in 2027.
  • Project expected to create ~3,000 construction jobs and 250 permanent positions and aims to reduce import reliance and generate foreign exchange savings.

Partnership and purpose

Danantara Investment Management (DIM), Indonesia Investment Authority (INA) and PT Chandra Asri Pacific Tbk completed a strategic investment transaction to develop a Chlor Alkali‑Ethylene Dichloride (CA‑EDC) project. The partnership combines the investment capabilities of DIM and INA with Chandra Asri Group's industrial experience, and is positioned to support Indonesia's downstreaming agenda by building local technical and operational expertise.

Project status and timeline

As of September 2026 construction was approximately 80% complete, with main equipment being installed and supporting infrastructure under development. The facility is targeted to commence commercial operations in 2027.

Capacity and intended impact

The plant is designed to produce approximately 400 kilotonnes per annum (KTA) of caustic soda and 500 KTA of ethylene dichloride (EDC). The project is expected to reduce reliance on imports, generate foreign exchange savings, and improve the availability of raw materials for downstream industries, strengthening domestic manufacturing capacity.

Employment

The project is expected to create approximately 3,000 jobs during the construction phase and 250 permanent positions during operations.

Source: Chandra Asri

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

29 September 2026
Chandra Asri CA‑EDC project 80% complete as main equipment installation begins

USD>800M CA‑EDC plant at 80% completion; main equipment being installed; start planned for 2027; capacities 827 kt caustic soda and 500 kt EDC with significant import substitution and export potential.

23 July 2026
Chandra Asri CA‑EDC project 72% complete, operations aimed for 2027

Construction of a Chlor‑Alkali and EDC plant is 72% complete; operations targeted for 2027 and Phase II planned with a $1bn investment.

7 May 2026
Chandra Asri Group advances CA‑EDC plant into jetty and storage tank construction

CA‑EDC now 66% complete and entering jetty and storage tank construction to support 827 kt/year caustic soda and 500 kt/year EDC; operations targeted Q1 2027.

3 March 2026
Danantara, INA and Chandra Asri back USD 800m CA‑EDC plant in Cilegon

Joint investment will fund local Caustic Soda and EDC capacity to cut import reliance and support downstream industrialisation.

20 February 2026
Chandra Asri Group reaches 50% completion of CA‑EDC plant