Chandra Asri CA‑EDC project 80% complete as main equipment installation begins

Key highlights
  • Project valued at more than USD800 million has reached about 80% completion and entered main equipment installation.
  • Equipment being installed includes process vessels, heat exchangers, pumps, compressors and absorption towers, plus a jetty, jetty trestle and storage facilities.
  • Targeted to commence operations in 2027 with annual capacities of 827,000 tonnes of liquid caustic soda and 500,000 tonnes of EDC.
  • Caustic soda could replace roughly USD293 million of imports per year while EDC is aimed at exports with about USD300 million potential foreign exchange annually.

Project status

The Chlor Alkali and Ethylene Dichloride (CA‑EDC) facility, developed by PT Chandra Asri Alkali (CAA), a subsidiary of PT Chandra Asri Pacific Tbk, reached approximately 80% construction completion as of September 2026 and has entered the main equipment installation phase. The project value exceeds USD800 million and is targeted to commence operations in 2027.

Equipment and infrastructure

Main equipment being installed comprises process vessels, heat exchangers, pumps, compressors and absorption towers. Site construction also includes a jetty, a jetty trestle and storage facilities to support operations and logistics.

Capacity and market impact

Once operational, the facility will produce up to 827,000 tonnes per year of liquid caustic soda and 500,000 tonnes per year of ethylene dichloride (EDC). The caustic soda output has the potential to replace imports valued at approximately USD293 million annually, while EDC production is intended for export with potential foreign exchange earnings of around USD300 million per year.

Employment and local sourcing

About 3,500 construction workers have been engaged on the project to date, with around 250 new workers expected to be absorbed when the plant starts operations. Thirty‑four micro, small and medium enterprises (MSMEs) from Warnasari and Samangraya villages have supplied food and beverage services for project workers.

Source: Chandra Asri

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

23 July 2026
Chandra Asri CA‑EDC project 72% complete, operations aimed for 2027

Construction of a Chlor‑Alkali and EDC plant is 72% complete; operations targeted for 2027 and Phase II planned with a $1bn investment.

7 May 2026
Chandra Asri Group advances CA‑EDC plant into jetty and storage tank construction

CA‑EDC now 66% complete and entering jetty and storage tank construction to support 827 kt/year caustic soda and 500 kt/year EDC; operations targeted Q1 2027.

3 March 2026
Danantara, INA and Chandra Asri back USD 800m CA‑EDC plant in Cilegon

Joint investment will fund local Caustic Soda and EDC capacity to cut import reliance and support downstream industrialisation.

20 February 2026
Chandra Asri Group reaches 50% completion of CA‑EDC plant

Chlor‑alkali/EDC plant hits 50% construction and aims for commercial start in Q1 2027; capacity 827,000 t caustic soda and 500,000 t EDC with import substitution and export value.

19 March 2025
Chandra Asri Group to build CA-EDC plant in Cilegon

IDR 15 trillion CA-EDC complex with 400kt caustic (solid)/827kt liquid and 500kt EDC yearly; 3,250 jobs; completion targeted for 2027; 2025 capex USD 350–400m.