At a glance
- The project began in early 2017 and will complete in the second half of 2019.
- The upgrade includes a new peracetic acid still and new reactors on stream 1.
- The construction phase starts in the New Year.
- The original plant was built in 1998.
Project Overview
Perstorp is investing in upgrading its original Caprolactone monomer plant in Warrington, UK. The new equipment will be constructed using state-of-the-art materials to future-proof production and enhance supply security.
Timeline and Construction
The project began in early 2017, with the construction phase of the new parts of the plant starting in the New Year. The upgrade includes installing a new peracetic acid still and new reactors on stream 1, which was originally built in 1998. The project is expected to be completed in the second half of 2019.
Operational Continuity
The replacement and upgrade will be conducted in a manner that does not impact current production, ensuring continuous operation throughout the construction period.