Union Chlorine awards EPC to FATA for 70 t/d Abu Dhabi chlor‑alkali plant

Key highlights
  • EPC contract awarded to FATA EPC for a greenfield 70 MT/day chlor‑alkali plant at ICAD‑3, Abu Dhabi.
  • Plant will produce 70 MT/day caustic soda (100%), hydrochloric acid and sodium hypochlorite in Phase‑I, with additional downstream products planned in Phase‑II targeting the oil & gas sector.
  • Facility will use state‑of‑the‑art bipolar membrane electrolysers and be designed to Best Available Techniques (BAT) for emissions and waste control to meet local environmental regulations.
  • Fast‑track schedule targets plant commissioning in August 2015 and commercial production in October 2015.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Union Chlorine chlor-alkali plant at ICAD-3 Abu Dhabi · United Arab Emirates
Operational / Completed
2013
2014
2015-08
2017-08-04

Project and partners

Union Chlorine L.L.C, a joint venture including Oman Chlorine SAOG and Horizon Energy L.L.C plus two other investors, has awarded an EPC contract to FATA EPC (a division of FATA SpA) for a greenfield chlor‑alkali plant to be built at ICAD‑3, ZonesCorpin, Abu Dhabi. The signing ceremony took place on November 12, 2013.

Scope and capacity

FATA EPC will deliver a full EPC scope including engineering, procurement, construction, commissioning and start‑up. The plant has an installed capacity of 70 metric tonnes per day (MT/day) of caustic soda at 100% and will produce hydrochloric acid and sodium hypochlorite in Phase‑I, with further downstream products planned for Phase‑II aimed at the oil & gas sector.

Technology and compliance

The facility will feature bipolar membrane electrolysers and is being designed according to Best Available Techniques (BAT) to control air emissions and waste processing, ensuring compliance with stringent local environmental regulations.

Market and schedule

The project is intended to supply high‑quality products to the UAE oil & gas market and other downstream industries, generate direct and supporting jobs, and follows a fast‑track timetable with commissioning targeted for August 2015 and commercial production for October 2015.

Source: omanchlorine.com

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

4 June 2026
Chlorum Solutions USA acquires Eddyville chlor-alkali facility

Acquisition secures a Midwest source of sodium hypochlorite, hydrochloric acid and caustic soda; staff retained and a $70M Arizona plant is under development.

10 December 2025
Chlorum Solutions USA to acquire Eddyville chlor-alkali plant from Cargill

Closing expected Q2 2026; facility uses membrane technology to make sodium hypochlorite, hydrochloric acid and caustic soda; current staff will remain.

17 December 2024
Chlorum Solutions USA to build first U.S. chlor-alkali plant in Casa Grande, Arizona

Small-scale $70M plant will use membrane electrolysis to make sodium hypochlorite, HCl and caustic soda for Arizona without storing liquefied chlorine, boosting local supply resilience.

21 April 2026
INEOS Inovyn to sell Italian chlor-alkali business to Esseco Industrial

Sale covers Rosignano and Tavazzano chlor‑alkali plants; regulatory approval required, expected 2026. Seller manages sites until closing; customer/supplier terms unchanged. Rosignano R&D retained.

29 July 2026
thyssenkrupp nucera delivers chlor-alkali plant to Chlorum Solutions in Palmeira, Brazil

Skid-mounted BM2.7 zero-gap membrane plant produces >15,000 tpy chlorine, runs on renewable electricity and follows a February commissioning of a similar unit.