thyssenkrupp nucera delivers chlor-alkali plant to Chlorum Solutions in Palmeira, Brazil

Key highlights
  • Skid-mounted chlor-alkali plant employs BM2.7 zero-gap membrane electrolysis technology.
  • Production capacity exceeds 15,000 tons of chlorine per year.
  • Plant is powered entirely by electricity from renewable energy sources.
  • Second Chlorum Solutions plant commissioned by thyssenkrupp nucera in 2026; a Minas Gerais unit was completed in February and both were engineered in parallel.
Related projects For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Chlorum Solutions chlor-alkali plant in Palmeira, Brazil · Brazil
Operational / Completed
2022-11-10
2026-03-25
2026-07-29
Chlorum Solutions chlor-alkali plant Uberlândia Brazil · Brazil
Operational / Completed
2022-11-10
2025-08
2026-02

Handover and commissioning

thyssenkrupp nucera has handed over a new chlor-alkali electrolysis plant to Chlorum Solutions at the Palmeira site. Commissioning was completed through close collaboration between thyssenkrupp nucera’s global project teams and Chlorum Solutions’ local organisation, with the skid-mounted concept and experienced teams ensuring operational readiness aligned with expectations.

Technology and design

The delivered system uses thyssenkrupp nucera’s BM2.7 zero-gap membrane electrolysis technology, noted for increased usable membrane area, full zero-gap design and low energy consumption. The plant is skid-mounted and built from standardized, pre-assembled modules installed on steel skids sized for container-standard transport, enabling faster, simpler assembly and lower construction costs.

Capacity and sustainability

The Palmeira facility provides a production capacity of more than 15,000 tons of chlorine per year. It was designed to meet stringent environmental and energy-efficiency requirements and is powered entirely by electricity from renewable energy sources.

Regional rollout

This is the second Chlorum Solutions chlor-alkali plant commissioned by thyssenkrupp nucera in 2026; an earlier skid-mounted BM2.7 unit in Minas Gerais was completed in February. Both projects were engineered and executed in parallel as part of Chlorum Solutions’ strategy to expand regional chlorine supply for products such as soda, hydrochloric acid and hypochlorite.

Source: thyssenkrupp nucera

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

17 December 2024
Chlorum Solutions USA to build first U.S. chlor-alkali plant in Casa Grande, Arizona

Small-scale $70M plant will use membrane electrolysis to make sodium hypochlorite, HCl and caustic soda for Arizona without storing liquefied chlorine, boosting local supply resilience.

4 June 2026
Chlorum Solutions USA acquires Eddyville chlor-alkali facility

Acquisition secures a Midwest source of sodium hypochlorite, hydrochloric acid and caustic soda; staff retained and a $70M Arizona plant is under development.

10 December 2025
Chlorum Solutions USA to acquire Eddyville chlor-alkali plant from Cargill

Closing expected Q2 2026; facility uses membrane technology to make sodium hypochlorite, hydrochloric acid and caustic soda; current staff will remain.

14 July 2026
Olin and Huntsman: SEC Declares S‑4 Effective for Planned Merger

SEC declared the Form S‑4 effective; special shareholder meetings set for Aug 25; closing expected H1 2027; transaction targets >$400M in synergies and broader vertical integration.

16 June 2026
Olin and Huntsman to merge as OlinHuntsman

All-stock merger creates an integrated North American chemicals platform with vertical chlorine/caustic integration, ~$12.5B pro forma revenue and $400M+ identified synergies.