Enagás H₂ Technical Day spotlights industry green hydrogen developments

Key highlights
  • Enagás will launch HyLoop+ in the second half of the year — billed as Europe’s first high‑pressure hydrogen flow metrology facility using a primary standard.
  • The world’s first large‑scale steelworks powered by green hydrogen is under construction, with its first phase due for completion this year and a related project planned in Portugal.
  • The Hydrogen Technology Observatory has grown to 110 members in two years, and 2026 was noted as a record year for advances across the hydrogen value chain.
  • Siemens Energy and other suppliers are scaling hydrogen turbines for combined‑cycle use and adapting existing models, while fuel cells are presented as a diesel replacement for suitably adapted ships.
Related projects For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Stegra Boden Green Steel Plant · Sweden
Announced / Concept
2021
—
—
—
—
Operational / Completed · expected date for subscribers
Stegra Sines Green Hydrogen Steel Plant · Portugal
FEED / Pre-FID
2024-09
2026-06
—
Under Construction · expected date for subscribers
—
—
Enagás HyLoop+ Hydrogen Flow Metrology Facility, Zaragoza · Spain
Under Construction
2024-04
2025-03
—
2026

Event overview

Enagás hosted the third H₂ Technical Day at its Corporate University in Madrid, convening national and international industrial, technological and academic experts to present green‑hydrogen decarbonisation projects and technological developments in industry and mobility. Arturo Gonzalo, Enagás CEO, framed the forum as an accelerator for technological development and noted the Hydrogen Technology Observatory now has 110 members.

Industrial deployment

Speakers reported pilot and scaling activity across the value chain. Gotzon Gómez presented the world’s first large‑scale steelworks powered by green hydrogen, with the first construction phase due this year and a further international project in Portugal. Siemens Energy described turbine developments for combined‑cycle applications and adaptations of existing models.

Mobility

Panelists discussed liquid hydrogen for trucking, evolving refuelling stations, alignment of vehicle uptake with supply, and maritime decarbonisation, with fuel cells positioned as a diesel replacement for appropriately adapted vessels.

Metrology and innovation

Enagás unveiled HyLoop+, its Metrology and Innovation Centre in Zaragoza, which will operate this year as Europe’s first high‑pressure hydrogen flow calibration facility using a primary standard. Sessions also showcased R&D and start‑up projects for fuel‑cell non‑road machinery, hydrogen vehicle conversions, and hydrogen‑combustion furnaces.

Source: Enagas Renovable

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

14 April 2026
thyssenkrupp-backed European Resilience Alliance launches to scale clean hydrogen deployment

CEO-led alliance white paper diagnoses bottlenecks—fragmented rules, high power costs, weak demand certainty—and urges bankable demand, simpler support, de-risk finance and cross-border infrastructure

14 April 2026
ERA launches to accelerate clean hydrogen for EU industrial competitiveness and energy independence

CEO-led alliance published a white paper urging governments to boost demand certainty, lower electricity costs, simplify RFNBO rules, de-risk finance and fund a hydrogen backbone to speed FIDs.

22 July 2026
Enagás raises stake in Saggas to 92.5% with €31m Osaka Gas buy

Purchase of additional stake in Sagunto LNG terminal pending approvals; aimed at supply security and integration with decarbonisation projects, expected before end‑2026.

17 September 2026
Moeve starts Onuba — 300 MW first phase of Andalusian Green Hydrogen Valley

First phase delivers 300 MW (option +105 MW), ~45,000 tH2/yr, >€1bn phase investment, €304m public support and an expected >8,000 jobs across the value chain.

5 October 2026
Enagás completes permanent sealing of Castor’s 13 wells

Permanently sealed 13 wells with three plugs each, seabed cleared and site prepared for final abandonment of surface facilities.