Its role Technology / equipment supplier
Also known as Cumic Steel Ltd.
chemXplore tracks 1 project involving CUMIC Steel, of which one is active.
1 more active project is in the record. See all 1 in chemXplore →
225,000 bbl/d oil capacity and 12 million m³/d gas processing; first of a six-platform series; P-80 and P-82 due to start production in 2027.
Two pre-salt platforms bound for the Búzios field will sail to Brazil for 2027 start-up; each can produce 225,000 b/d and treat 12 million m³/d of gas.
Quarterly results bolstered by record own oil output, above-100% refinery utilization and higher derivative production, supporting cash generation and lower imports.
Record reached after P-78 and P-79 began ramping up; field operates eight production units and plans 12 FPSOs.
active all projects