Uniper appoints Worley as preferred EPC for Connah’s Quay low-carbon power project

Key highlights
  • Worley named preferred EPC after a FEED competition that began in December 2024.
  • Uniper submitted a Development Consent Order in August 2025; a decision is expected in the coming months.
  • The plant would fit carbon capture to remove at least 95% of CO2 and link into HyNet CO2 transport and offshore storage.
  • Target capacity up to 1.38 GW; phase one could be operational from 2030 and supply about 1.1 million homes.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Uniper Connah's Quay Low Carbon Power Project · United Kingdom
FEED / Pre-FID
2024
2024-12
—
—
—
Operational / Completed · expected date for subscribers

Contract award and FEED conclusion

Worley has been selected as the preferred Engineering, Procurement and Construction (EPC) supplier for Uniper’s proposed Connah’s Quay Low Carbon Power (CQLCP) project following a Front End Engineering Design (FEED) competition that started in December 2024. Uniper announced the decision on 23 July.

Permitting and next milestones

Uniper submitted a Development Consent Order (DCO) application in August 2025; a decision is expected in the coming months. If consented and developed, the new station would be built on land adjacent to Uniper’s existing power station and progress toward a final investment decision.

Carbon capture and cluster integration

The proposed station would be fitted with carbon capture technology designed to capture at least 95% of its CO2 emissions and connect into CO2 transport and storage infrastructure within the HyNet industrial cluster, enabling permanent offshore storage in repurposed depleted gas fields.

Capacity and timing

The project targets up to a maximum of 1.38 GW of low‑carbon power developed in two phases; from completion of phase one the scheme could supply the equivalent of around 1.1 million homes a year, with phase one potentially operational from 2030.

Source: Worley

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

28 July 2026
Uniper selects SLB Capturi Big Catch for Connah’s Quay low‑carbon power

Preferred carbon-capture tech chosen for proposed Connah’s Quay project; configured for flexible gas‑turbine operation, tied to HyNet CO2 pipeline, up to 1.38 GW in two phases.

17 July 2026
Uniper to invest €5 billion in European energy system transformation

Focus on flexible generation, hydrogen-ready plants, renewables and gas diversification; projects include ~1.7 GW of tendered plants, data‑centre site development and gas portfolio expansion.

8 December 2025
Worley to Build UK's First Cement Carbon Capture Facility

The facility will capture 800,000 tonnes of CO2 annually, aiming for net zero cement production by 2029, supporting UK decarbonization and creating jobs in North Wales.

8 October 2026
Eni CCUS Holding: Douglas CCS — first offshore CO₂ transport and storage platform

New offshore hub will collect CO₂ from North West England and North Wales and route it via repurposed pipelines to depleted gas reservoirs; delivered in under 18 months; project ~50% complete.

31 August 2026
Uniper advances NorthStarH2 into FEED with AFRY, Carbon Clean, Siemens Energy and Topsoe

Contracts worth >SEK100m launch ~1-year FEED for a 115,000 t/yr e‑methanol plant using renewable electricity and biogenic CO2; FID 2028, commissioning 2031.