Uniper advances NorthStarH2 into FEED with AFRY, Carbon Clean, Siemens Energy and Topsoe

Key highlights
  • Uniper contracted AFRY, Carbon Clean, Siemens Energy and Topsoe to carry out the FEED phase for NorthStarH2.
  • Contracts total more than SEK 100 million and the FEED work will run for approximately one year.
  • NorthStarH2 is designed to produce about 115,000 tonnes of e‑methanol per year from renewable electricity and biogenic CO2.
  • Uniper targets a final investment decision in 2028, commissioning in 2031, and an environmental permit application in autumn 2026.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Uniper NorthStarH2 e-methanol plant in Östersund · Sweden
FEED / Pre-FID
2024
2026-08-31
FID / Sanctioned · expected date for subscribers
—
Commissioning & Start-up · expected date for subscribers
—

FEED contracts

Uniper has signed contracts with AFRY, Carbon Clean, Siemens Energy and Topsoe to begin the Front‑End Engineering Design (FEED) phase for the NorthStarH2 e‑methanol project in Östersund.

Scope and budget

The contracts are worth more than SEK 100 million in total and the FEED work will run for approximately one year. Suppliers will provide engineering expertise for electrolysis, carbon capture, methanol synthesis and purification.

Plant output and inputs

NorthStarH2 will use renewable electricity and biogenic carbon dioxide to produce fossil‑free e‑methanol, with planned annual production of approximately 115,000 tonnes. The e‑methanol is intended to replace fossil fuels in sectors such as transport and the chemical industry.

Project schedule and permitting

Uniper plans a final investment decision in 2028 and currently schedules commissioning to begin in 2031. The company intends to submit its environmental permit application in autumn 2026.

Source: Uniper

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

31 August 2026
Topsoe to deliver FEED for Uniper's NorthStarH2 e‑methanol project

115,000 t/y e‑methanol plant in Östersund using modular ModuLite tech; FID targeted 2028; will combine renewable hydrogen with biogenic CO₂ and use existing road/rail logistics.

31 August 2026
AFRY to lead FEED for Uniper NorthStarH2 e‑methanol plant

FEED covers process design, plant engineering, HSE and OEM coordination for a 115,000 t/y e‑methanol plant using 175 MW electrolysis and biogenic CO₂.

6 October 2026
Carbon Clean joins Net Zero Start‑Up Hub to pilot compact CO2 capture for data centres

Selected for a six‑month incubation to test a modular carbon capture unit designed for space‑constrained data centre power plants.

3 September 2026
ORLEN launches Baltic Energy Initiative with 13 regional partners

Regional platform mobilises 14 organisations to coordinate offshore wind, LNG/bioLNG, hydrogen, CCS, SMRs and infrastructure protection across the Baltic Sea region.

28 July 2026
Uniper selects SLB Capturi Big Catch for Connah’s Quay low‑carbon power

Preferred carbon-capture tech chosen for proposed Connah’s Quay project; configured for flexible gas‑turbine operation, tied to HyNet CO2 pipeline, up to 1.38 GW in two phases.