AFRY to lead FEED for Uniper NorthStarH2 e‑methanol plant

Key highlights
  • Planned output: around 115,000 tonnes of e‑methanol per year.
  • Hydrogen produced by electrolysis powered by 175 MW of renewable electricity, with biogenic CO₂ captured from Jämtkraft’s Lugnvik biomass CHP.
  • AFRY will deliver a complete technical FEED including process design, plant engineering, operating philosophy, technical specifications, HSE in Design and OEM coordination.
  • Schedule: FEED kicked off late August 2026 and runs to Summer 2027; Uniper plans FID in 2028 and commissioning in 2031.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Uniper NorthStarH2 e-methanol plant in Östersund · Sweden
FEED / Pre-FID
2024-01-30
2026-08-31
FID / Sanctioned · expected date for subscribers
—
Commissioning & Start-up · expected date for subscribers
—

Project overview

AFRY has been awarded the FEED for NorthStarH2, an e‑methanol production facility planned for Östersund, Sweden. The plant is designed to produce around 115,000 tonnes of e‑methanol per year to cut fossil emissions in hard‑to‑abate sectors such as transport and the chemical industry.

Feedstocks and process

Green hydrogen will be produced through electrolysis powered by 175 MW of renewable electricity. That hydrogen will be combined with biogenic CO₂ captured from Jämtkraft’s biomass‑fired heat and power plant in Lugnvik to deliver fossil‑free methanol made from renewable power and recycled biogenic carbon.

AFRY scope

AFRY’s assignment is a complete technical FEED covering strategies, plans and a cost estimate. The scope explicitly includes process design, plant engineering, operating philosophy, technical specifications, HSE in Design and coordination with OEM suppliers for electrolysis, carbon capture and methanol synthesis.

Timing and partners

The FEED work kicked off late August 2026 and is expected to run until Summer 2027, taking the project from early development towards a Final Investment Decision planned for 2028, with commissioning currently scheduled for 2031. NorthStarH2 is driven by Uniper through Sydkraft Hydrogen AB in cooperation with Jämtkraft.

Stakeholder remarks

"E‑methanol will play an increasingly important role in decarbonizing hard‑to‑abate sectors such as transport and chemicals. AFRY is honored to support Uniper in transforming this vision into a technically robust and investment‑ready project," says Guy Skantze at AFRY.

"NorthStarH2 is an important project in Uniper’s energy transition portfolio, and we are pleased that the FEED contract with AFRY is now in place. We look forward to continuing our successful collaboration and completing the FEED phase together," says Broghan Helgeson, NorthStarH2’s project manager at Uniper.

Source: AFRY

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

9 November 2026
Uniper files environmental permit for NorthStarH2 e‑methanol project

Seeks approval for a plant to produce about 115,000 t/y e‑methanol and reuse ~160,000 t/y biogenic CO2; FID 2028, commissioning planned from 2031.

31 August 2026
Topsoe to deliver FEED for Uniper's NorthStarH2 e‑methanol project

115,000 t/y e‑methanol plant in Östersund using modular ModuLite tech; FID targeted 2028; will combine renewable hydrogen with biogenic CO₂ and use existing road/rail logistics.

31 August 2026
Uniper advances NorthStarH2 into FEED with AFRY, Carbon Clean, Siemens Energy and Topsoe

Contracts worth >SEK100m launch ~1-year FEED for a 115,000 t/yr e‑methanol plant using renewable electricity and biogenic CO2; FID 2028, commissioning 2031.

18 February 2026
VolagHy Releases EIA Program for Kuopio Site

The EIA program for the Kuopio site outlines environmental, social, and land-use assessments, moving the project into the formal evaluation phase with stakeholder engagement.

25 November 2026
Uniper to invest €120m in Bierwang gas storage upgrade

The programme targets faster filling, higher withdrawal capacity and roughly 60% lower site emissions.