thyssenkrupp Steel opens hydrogen tender for Duisburg direct reduction plant

Key highlights
  • The first procurement tranche is expected to cover 20,000–40,000 tonnes of hydrogen per year.
  • Deliveries are planned to start in 2031; suppliers can register until December 17, 2026.
  • The direct reduction plant is designed to produce 2.5 million tonnes of DRI annually.
  • Full hydrogen operation could avoid about 3.5 million tonnes of CO₂ emissions per year versus blast furnace production.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
thyssenkrupp Steel 2.5 Mtpa DRI Plant Duisburg · Germany
Under Construction
2020-08
2022-09-08
2024-01
Commissioning & Start-up · expected date for subscribers
—

Hydrogen procurement

thyssenkrupp Steel has launched a tender to supply its Duisburg direct reduction plant. The first tranche is expected to cover 20,000–40,000 tonnes of hydrogen per year, with deliveries starting in 2031. The awarded volume will depend on bids and their commercial terms. Suppliers can register until December 17, 2026, before the bidding phase begins.

Phased introduction

The plant will initially use natural gas during ramp-up, reducing CO₂ emissions by more than 50% even at this stage. From 2031, hydrogen will gradually replace some natural gas, with full hydrogen operation planned later. This phased approach follows European Commission state aid requirements and the current grant approval from the German federal government and North Rhine-Westphalia.

Plant capacity and emissions

The direct reduction plant is designed to produce 2.5 million tonnes of direct reduced iron annually. Two downstream smelters have a combined capacity of 2.3 million tonnes of hot metal per year. At full hydrogen operation, the facility could avoid approximately 3.5 million tonnes of CO₂ emissions annually compared with blast furnace production.

Source: thyssenkrupp

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

30 October 2026
thyssenkrupp Steel: definitive revised funding decision for tkH2Steel

Revision enables phased hydrogen ramp-up and planning certainty; new hydrogen tender to start soon. 2.5 Mt/y direct reduction plant aims to avoid up to 3.5 Mt CO2 annually.

28 September 2026
thyssenkrupp Steel reaffirms strategy and sets medium-term targets

Targets adjusted EBITDA ≥€1.2bn, an 11% margin and positive free cash flow; expects >€800m EBITDA uplift from self‑help measures and has implemented major restructuring steps.

26 November 2025
Uniper and thyssenkrupp Uhde Partner on Ammonia Cracking for Hydrogen Import

Framework agreement signed for ammonia cracking plants to support hydrogen import infrastructure, aiming to decarbonize industry and enhance Europe's energy resilience.

17 June 2026
ArcelorMittal, thyssenkrupp Steel and voestalpine urge ETS reform to protect EU steelmaking

They want a temporary pause in ETS cost increases, funding and support for first movers, and measures to address import/export competitiveness to preserve European steel value chains.

29 October 2026
thyssenkrupp Uhde to deliver FEED study for CF Industries' Courtright urea liquor upgrade

FEED study assesses urea liquor upgrade at Courtright, Ontario, which could add more than 400,000 short tons/year of diesel exhaust fluid capacity if FID is positive.