BarMar enters FEED for H2med Barcelona–Marseille hydrogen pipeline

Key highlights
  • BarMar project has entered the FEED phase to finalise pipeline design, route and compression station layout.
  • The offshore corridor will connect Barcelona and Marseille for green hydrogen transport.
  • The H2med–BarMar project received over €28 million from the CEF in January 2025 to fund engineering, surveys and permit work.
  • FEED will provide the technical basis for partners’ FID ahead of a planned commercial start in 2032.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
BarMar H2med Barcelona-Marseille Hydrogen Pipeline · France
FEED / Pre-FID
2022
2026-07
FID / Sanctioned · expected date for subscribers
Under Construction · expected date for subscribers
Commissioning & Start-up · expected date for subscribers
Operational / Completed · expected date for subscribers

FEED launch and technical scope

The BarMar offshore pipeline project has moved from pre‑FEED to the Front‑End Engineering Design phase. Pre‑FEED confirmed overall technical feasibility and established the design basis for the pipeline and compression station; an advanced corridor route has been defined using initial environmental impact assessment findings, which remain ongoing.

What FEED will deliver

FEED will confirm the pipeline design and final route, finalise the compression station layout, prepare permitting files and define technical specifications for construction preparation and material procurement. The next contractual steps are awarding the FEED engineering package and an offshore detailed marine survey. Results from these studies will form the technical basis for partners and investors to take a Final Investment Decision ahead of construction.

Funding, schedule and political context

Under CEF funding allocated in January 2025, H2med–BarMar benefited from over €28 million to finance engineering studies, marine and environmental surveys, environmental impact assessments and permit activities. The public consultation in France and Spain concluded in July 2026; in France the concertation guarantors will publish a feedback report with recommendations for promoters. A ministerial meeting on 6 July in Paris, attended by energy ministers from Portugal, France and Spain, European Energy Commissioner Dan Jørgensen, regulators, operators and Germany (present for the first time in the group), underlined political momentum for the H2med corridor, which aims for commissioning in 2032 provided regulatory conditions are met.

Source: Enagas Renovable

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

30 September 2025
Repsol's First Large-Scale Renewable Hydrogen Plant in Cartagena

A 100 MW electrolyzer in Cartagena will produce 15,000 tonnes of renewable hydrogen annually, cutting 167,000 tonnes of CO2 emissions, with €155 million in EU funding. Operational by 2029.

17 September 2026
Moeve starts Onuba — 300 MW first phase of Andalusian Green Hydrogen Valley

First phase delivers 300 MW (option +105 MW), ~45,000 tH2/yr, >€1bn phase investment, €304m public support and an expected >8,000 jobs across the value chain.

16 September 2026
Moeve brings Hy24 and COFIDES into Onuba phase of Andalusian Green Hydrogen Valley

First phase includes a 300 MW electrolyser (>€1bn capex), ~45,000 t H2/yr and ~250,000 t CO2 avoided; received €304m public funding and reached FID.

22 July 2026
Enagás raises stake in Saggas to 92.5% with €31m Osaka Gas buy

Purchase of additional stake in Sagunto LNG terminal pending approvals; aimed at supply security and integration with decarbonisation projects, expected before end‑2026.

11 June 2026
Enagás launches public participation plan for 44 km hydrogen backbone in Murcia

Conceptual public participation plan opened for a 44 km hydrogen pipeline in Murcia, with local events and info points; part of Spain’s wider 2,600 km Hydrogen Backbone programme.