EnviTec Biogas advances three biomethane projects in Germany

Key highlights
  • Priborn plant (in operation since 2004) fitted with an EnviThan upgrader at 475 Nm³/h alongside PreMix mixing, new digestate tanks and other ancillary systems.
  • Friesoythe conversion repurposes a former 370 kW co‑fermentation plant after 22 years and EEG expiry (1 Jan 2025); initial raw biogas design 500 Nm³/h, expandable to 600 Nm³/h, to inject into EWE NETZ.
  • Delbrück will host a 200 Nm³/h membrane upgrading unit in a 45‑foot container using 4‑ and 6‑inch membranes; container delivery in the second week of September and first feed‑in scheduled for November.
  • Projects rely on renewable raw materials, slurry and manure, illustrating conversion of agricultural biogas assets to grid‑injected biomethane and local energy uses.
Related projects For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
EnviTec Biogas Priborn Biomethane Upgrade · Germany
Operational / Completed
2026-07
EnviTec Friesoythe Biomethane Conversion, Germany · Germany
Announced / Concept
2026-09-16
—
—
—
—
—
EnviTec Biogas Delbrück Biomethane Upgrade, Germany · Germany
Under Construction
2026-09
Commissioning & Start-up · expected date for subscribers
—

Project updates

EnviTec’s Priborn site began upgrading biogas to biomethane in July. The plant, in operation since 2004 and formerly with a 550 kWel electrical output, was expanded with an EnviThan gas upgrader rated 475 Nm³/h and fitted with PreMix mixing technology, a push floor system, a technical building, an oxygen generator, three digestate storage tanks with two filling stations, a pump house, a separation unit and an additional emergency flare.

At Friesoythe, after 22 years of biogas production and the expiry of EEG remuneration on 1 January 2025, a former 370 kW co‑fermentation plant is being converted for biomethane injection to the local gas grid operated by EWE NETZ. The first expansion stage targets 500 Nm³/h of raw biogas, with a potential long‑term capacity of 600 Nm³/h, using farm slurry, manure and renewable raw materials as feedstocks.

Containerised upgrade and timing

In Delbrück a customer‑owned plant will be fitted with a 200 Nm³/h upgrading unit housed in a 45‑foot container, equipped with 4‑ and 6‑inch membranes. The container is due for delivery in the second week of September, with the first feed‑in scheduled for November; the owners already run a combined heat and power unit and will inject biomethane into the local grid.

Role of biomethane

Biomethane is produced by upgrading biogas from organic residues and renewable raw materials to a composition nearly identical to fossil natural gas, enabling its use for electricity and heat generation, transport fuel and industrial processes while reducing greenhouse gas emissions and fossil dependence.

Source: EnviTec Biogas

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

21 January 2026
EnviTec Biogas Launches New Plant in Cremona

The new plant in Soncino feeds 237 Nm³/h of biomethane into the grid. EnviTec expands projects in Italy, aligning with PNRR goals and eco-efficiency trends.

9 July 2026
EnviTec Biogas opens first integrated biogas‑to‑biomethane plant in Estonia

Combined biogas and membrane upgrading plant produces ~600 Nm³/h biomethane from dairy slurry; digestate reused in agriculture and CNG refuelling supplies regional transport.

13 May 2026
EnviTec Biogas opens Bio-LNG filling station in Holdorf

New Bio-LNG station in Holdorf offers A1/B214 access, 30,000 kg storage and two pumps; supports LNG truck fleet, enabling ~200 t CO2 savings per truck/year (at 125,000 km).

19 March 2026
EnviTec Biogas and LIQVIS expand Bio‑LNG network

Bio-LNG: low-emission, price-stable heavy-truck fuel—up to 1,700 km range, ~15-min refuel, <€1/kg; made from local organic feedstocks and rolled out via expanding station network

30 September 2025
EnviTec Biogas Reports Stable H1 2025 Performance Amid Market Challenges

H1 2025 saw steady Own Plant Operation, but Plant Construction faced setbacks. Strategic investments and acquisitions aim to boost future growth.