Avantium starts up Delfzijl FDCA Flagship Plant with first FDCA batch produced

Key highlights
  • Avantium produced the first batch of FDCA at its FDCA Flagship Plant in Delfzijl, the world’s first commercial-scale FDCA plant.
  • All major process units have been commissioned, marking the transition from commissioning to operational start-up and qualification.
  • Avantium will run a disciplined product qualification and operating program, moving from batch toward continuous operations and preparing for commercial sales expected toward the end of 2026.
  • Ramp-up to full design capacity is expected to take 12–24 months and should validate the YXY® Technology and support licensing discussions with partners.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Avantium FDCA Flagship Plant at Delfzijl · The Netherlands
Commissioning & Start-up
2020-01
2021
2021-12
2022-04
2026-09
Operational / Completed · expected date for subscribers

Start-up milestone

Avantium has produced the first batch of furandicarboxylic acid (FDCA) at its FDCA Flagship Plant in Delfzijl, described as the world’s first commercial-scale FDCA plant. The company reports successful commissioning of all major process units, and views the first-batch production as a major start-up milestone that moves activities from commissioning to operational start-up and qualification.

Qualification and initial operations

Avantium will focus on a disciplined product qualification and operating programme to ensure FDCA meets customer specifications, progressing from batch toward continuous operations. Management says teams will optimise operations, produce additional FDCA and complete qualification activities as part of preparing for commercial sales.

Ramp-up, capacity and commercial outlook

Commercial sales are anticipated to start toward the end of 2026. The company expects ramp-up to full design capacity to take 12–24 months after plant start-up. A successful start-up and qualification process is expected to provide commercial-scale validation of Avantium’s YXY® Technology for FDCA and PEF and to support advancement of licensing discussions with prospective partners worldwide.

Source: Avantium

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

7 September 2026
Avantium commissions purification unit at Delfzijl FDCA flagship plant

Purification unit brought online, completing commissioning of all major process units; integrated start-up moves toward first FDCA production and end‑2026 commercial deliveries.

19 August 2026
Avantium advances FDCA Flagship Plant start-up and readies financing package

Oxidation unit commissioned; full start-up and first FDCA production targeted end‑2026; 22 offtakes and >150 kt reservations secured; pursuing €55m equity plus a €20m NOM loan.

30 April 2026
Avantium completes titanium weld repairs at FDCA flagship plant

Weld repairs completed with engineering partners. Commissioning continues: utilities and sugar dehydration online; oxidation and purification in final start-up. Commercial sales expected H2 2026

23 January 2026
Avantium Updates on FDCA Plant Start-Up

Start-up delayed to mid-2026 due to titanium weld issues, adding €7M in costs. Sales to begin in the second half of 2026.

29 August 2025
Avantium Launches FDCA Flagship Plant's SDH Unit