Avantium commissions purification unit at Delfzijl FDCA flagship plant

Key highlights
  • Purification unit at the Delfzijl FDCA Flagship Plant has been commissioned, completing commissioning of all major process units.
  • This follows prior start-up of utility systems and the sugar dehydration unit and successful commissioning of the oxidation unit.
  • Avantium is proceeding with integrated start-up, preparing for first FDCA batches and completing product qualification.
  • Commercial deliveries under existing offtake agreements are expected to begin end‑2026 subject to successful start‑up and qualification; ramp‑up to full design capacity is expected to take ~24 months after start‑up.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Avantium FDCA Flagship Plant at Delfzijl · The Netherlands
Commissioning & Start-up
2020-01
2021
2021-12
2022-04
2026-09
Operational / Completed · expected date for subscribers

Commissioning milestone

Avantium has completed commissioning of the purification unit at its FDCA Flagship Plant in Delfzijl, marking the successful commissioning of all major process units at the world's first commercial‑scale FDCA plant.

The purification unit follows the previously announced start‑up of utility systems and the sugar dehydration unit, and the successful commissioning of the oxidation unit.

Next steps

The company is now continuing integrated start‑up activities and preparing for the production of the first batches of FDCA while completing qualification activities. Hero de Jager, interim Chief Operations Officer, said the company's focus shifts to producing the first batches and to commencing commercial deliveries under existing offtake agreements as planned.

Commercial ramp‑up

Avantium expects commercial deliveries under existing offtake agreements to commence at the end of 2026, subject to successful start‑up and product qualification. Ramp‑up to full design capacity is expected to take approximately 24 months following start‑up, and successful completion of start‑up is anticipated to provide commercial‑scale validation of the FDCA technology and support licensing discussions.

Source: Avantium

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

30 September 2026
Avantium publishes H1 2026 financials and completes Worley close-out for FDCA Flagship Plant

H1: revenues €4.7m, EBITDA -€18.8m, cash €23.9m; first FDCA batch produced; planned equity raise ≥€55m and proposed €20m facility; Worley contractual close‑out finalised.

28 September 2026
Avantium starts up Delfzijl FDCA Flagship Plant with first FDCA batch produced

First FDCA batch produced at Delfzijl; product qualification begins with aim for commercial sales by end of 2026.

19 August 2026
Avantium advances FDCA Flagship Plant start-up and readies financing package

Oxidation unit commissioned; full start-up and first FDCA production targeted end‑2026; 22 offtakes and >150 kt reservations secured; pursuing €55m equity plus a €20m NOM loan.

30 April 2026
Avantium completes titanium weld repairs at FDCA flagship plant

Weld repairs completed with engineering partners. Commissioning continues: utilities and sugar dehydration online; oxidation and purification in final start-up. Commercial sales expected H2 2026

23 January 2026
Avantium Updates on FDCA Plant Start-Up

Start-up delayed to mid-2026 due to titanium weld issues, adding €7M in costs. Sales to begin in the second half of 2026.