Avantium completes titanium weld repairs at FDCA flagship plant

Key highlights
  • Titanium weld defects at Avantium's FDCA Flagship Plant were fully repaired by SRI Speciaal Roestvrijstaal Industrie under Bilfinger supervision.
  • Utilities and the Sugar DeHydration unit are operational, with oxidation and purification units in final commissioning.
  • Commercial sales remain on track to start in H2 2026; the plant produces FDCA for PEF production.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Avantium FDCA Flagship Plant at Delfzijl · The Netherlands
Commissioning & Start-up
2020-01
2021
2021-12
2022-04
2026-09
Operational / Completed · expected date for subscribers

Weld repair completion

Avantium has fully resolved construction‑related titanium weld issues at its FDCA Flagship Plant; remediation met the required quality and safety standards.

Execution and oversight

Repair work was executed by SRI Speciaal Roestvrijstaal Industrie (Veenwouden) under the supervision of Bilfinger.

Commissioning status

Commissioning continues: utilities and the Sugar DeHydration unit are operational, while the oxidation and purification units are in final commissioning and start‑up stages.

Schedule and commercial outlook

Avantium states the expected timelines for plant start‑up and offtake sales remain unchanged, with commercial product sales expected in H2 2026.

Source: Avantium

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

30 September 2026
Avantium publishes H1 2026 financials and completes Worley close-out for FDCA Flagship Plant

H1: revenues €4.7m, EBITDA -€18.8m, cash €23.9m; first FDCA batch produced; planned equity raise ≥€55m and proposed €20m facility; Worley contractual close‑out finalised.

28 September 2026
Avantium starts up Delfzijl FDCA Flagship Plant with first FDCA batch produced

First FDCA batch produced at Delfzijl; product qualification begins with aim for commercial sales by end of 2026.

7 September 2026
Avantium commissions purification unit at Delfzijl FDCA flagship plant

Purification unit brought online, completing commissioning of all major process units; integrated start-up moves toward first FDCA production and end‑2026 commercial deliveries.

19 August 2026
Avantium advances FDCA Flagship Plant start-up and readies financing package

Oxidation unit commissioned; full start-up and first FDCA production targeted end‑2026; 22 offtakes and >150 kt reservations secured; pursuing €55m equity plus a €20m NOM loan.

23 January 2026
Avantium Updates on FDCA Plant Start-Up

Start-up delayed to mid-2026 due to titanium weld issues, adding €7M in costs. Sales to begin in the second half of 2026.