Uniper: Wilhelmshaven power plant decommissioned to free site for new energy projects

Key highlights
  • Decommissioning began with contractor handover in early October and is expected to finish by the end of 2029.
  • The 275-metre-high chimney is scheduled for demolition in spring 2027.
  • Site redevelopment across roughly 100 hectares includes a 17 MWp solar park and a 50 MW / 100 MWh battery energy storage system (BESS).
  • Delivery of 26 batteries for the BESS from the Heyden site is scheduled for October.
Related projects For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Uniper NGEN Wilhelmshaven 50 MW (100 MWh) BESS · Germany
Under Construction
~2025
2026-04
—
2026 Q4
Uniper Wilhelmshaven 200 MW Green Hydrogen Electrolyser · Germany
FEED / Pre-FID
2024-04
2024-10
—
—
—
Operational / Completed · expected date for subscribers
Uniper Voslapper Groden Solar Park Wilhelmshaven · Germany
Commissioning & Start-up
2023
2024-04-30
2025-10-30
2025-11
2026-07
Operational / Completed · expected date for subscribers
+ 1 more tracked in chemXplore

Background

The Wilhelmshaven hard coal-fired power station was commissioned on 24 September 1976 and ran for 45 years, with a final capacity of 777 MW. Electricity production ended with decommissioning on 7 December 2021; over its lifetime the plant burned more than 58 million tonnes of coal and generated over 151 million MWh.

Decommissioning plan

Handover to decommissioning contractors took place at the start of October and work is scheduled to conclude by the end of 2029. A key milestone is the planned demolition of the 275-metre chimney in spring 2027. Decontamination will precede mechanical demolition, which will use specialised long-reach excavators to minimise working at height; selected buildings and facilities needed for future use will be retained.

Site redevelopment

The approximately 100-hectare site is being repurposed for new energy and industrial projects. The Voslapper Groden solar park on the former ash tip is nearing completion at about 17 MWp. A 50 MW / 100 MWh BESS is under construction, with 26 batteries due to be delivered from Heyden in October. Planned projects include a large-scale electrolysis plant for renewable hydrogen linked to future hydrogen infrastructure within the Energy Transformation Hub North-West.

Training and retention

The on-site workshop and longstanding training centre will be retained and developed as a training and further education centre to support technical workforce development for the energy transition.

Source: Uniper

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

9 April 2026
Uniper and NGEN break ground on 50 MW (100 MWh) battery in Wilhelmshaven

The new facility will balance short-term wind/solar fluctuations, boost grid stability and renewable integration. Commissioning planned Q4 2026. Local officials attended; public updates online.

4 February 2026
Uniper's 10-Year Solar PPA with NKT in Wilhelmshaven

The 17.2 MWp solar park will supply renewable energy to NKT's Nordenham and Cologne facilities, enhancing sustainability and regional energy use.

11 December 2025
Uniper's 50 MW Battery Storage Approved at Wilhelmshaven

The facility will enhance grid stability and support renewable integration. A solar plant is also under construction, with commissioning set for July 2026.