Uniper Chooses Plug for 100MW Electrolyzer at Rotterdam Maasvlakte Plant

Key highlights
  • Uniper plans to commission 100 MW of Plug electrolysis capacity by 2026, expanding to 500 MW by 2030.
  • The Rotterdam Harbor area emitted 23.4 Mton CO2 in 2021.
  • Plug will deliver 10 prefabricated PEM electrolyzer arrays for the H2Maasvlakte project.
  • The FEED study is supported by Topsector Energie subsidies from the Dutch Ministry of Economic Affairs and Climate.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Shell Holland Hydrogen 1 Rotterdam Maasvlakte · The Netherlands
Under Construction
2021
2022
2022 Q1
2026
Operational / Completed · expected date for subscribers

Project Overview

Uniper has selected Plug Power to design the electrolyzer technology for its Maasvlakte site at the Port of Rotterdam. The project aims to commission 100 MW of Plug electrolysis capacity by 2026, with plans to expand to 500 MW by 2030.

Decarbonization Efforts

The Rotterdam Harbor area, including Maasvlakte, is the largest carbon-emitting industrial cluster in the Netherlands, emitting 23.4 Mton CO2 in 2021. Decarbonizing this area is crucial for the Netherlands to achieve its net-zero target by 2050.

Technology and Implementation

Under the agreement, Plug will deliver 10 prefabricated PEM electrolyzer arrays for Uniper’s H2Maasvlakte project. The electrolyzer technology will be manufactured in the European Union and the United States.

Support and Funding

The H2Maasvlakte project is part of the Front-End Engineering Design (FEED) study conducted by Uniper with Technip Energies. The study is supported by Topsector Energie subsidies from the Dutch Ministry of Economic Affairs and Climate.

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

12 August 2026
PM Jetten visits Port of Rotterdam Authority at Maasvlakte

Inspected a container terminal, discussed hundreds‑million‑euro investment plans and constraints with industry, and toured Shell’s Holland Hydrogen 1 green‑hydrogen facility.

29 September 2026
Plug Power and Arcadia eFuels partner for >1 GW e‑SAF electrolyzer supply; 280 MW for Denmark ENDOR

Preferred electrolyzer supplier for over 1 GW of e‑SAF projects; initial 280 MW GenEco will produce ~110 t/day renewable H2 for jet fuel at Port of Vordingborg; ENDOR moving to FID.

22 September 2026
Plug Power ships 1 MW GenEco electrolyzer to HWR Hydrogen in New Zealand

The 1 MW PEM electrolyzer will produce hydrogen for a refuelling station to supply dual‑fuel heavy trucks and help build South Island hydrogen infrastructure.

10 August 2026
Plug Power Q2 2026: ~$178M Revenue, ~Breakeven Gross Margin, Improved Cash Position

Sequential revenue growth, gross-margin expansion to breakeven, operating costs cut ~50%, raised 2026 revenue guidance to 15–16% and targets positive EBITDAS in Q4.

30 January 2026
Rotterdam Hydrogen Pipeline Filled by Gasunie

Rotterdam's hydrogen pipeline is filled with 32 tonnes of green hydrogen, linking the port to industrial users and connecting to broader European hydrogen infrastructure.