thyssenkrupp nucera opens company-operated electrolyzer cell Assembly Hub in Portugal

Key highlights
  • thyssenkrupp nucera will open a company-operated Assembly Hub in VGP Park Vila Nova de Gaia, Portugal, in a 7,500+ m² building.
  • Construction starts winter 2026; cell assembly on the semi-automated line will begin in 2028.
  • Investment is EUR 10–14 million, supported by about EUR 3.7 million from the Portuguese COMPETE2030 program.
  • The Hub will assemble alkaline water electrolysis cells, including scalum® 20 MW units, initially supplying Moeve's Onuba project.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
thyssenkrupp nucera Electrolyzer Cell Assembly Hub Vila Nova de Gaia · Portugal
Announced / Concept
2026-10-06
—
—
2026
—
Operational / Completed · expected date for subscribers

Project overview

thyssenkrupp nucera is establishing its first company-operated central Assembly Hub for electrolyzer cells in VGP Park Vila Nova de Gaia, Portugal, consolidating cell assembly at a single, central location.

Timeline and financing

Construction of the more than 7,500 m² building begins in winter 2026. An assembly line will be installed and cell assembly will start in 2028. thyssenkrupp nucera is investing between EUR 10 million and EUR 14 million, with approximately EUR 3.7 million in support from Portugal's COMPETE2030 program.

Operations and capacity

The Hub will use standardized, semi-automated production-line processes to increase throughput and reduce lead times compared with manual, decentralized assembly. Initially, the site will assemble cells for alkaline water electrolysis and scalum®, the standardized 20 MW unit, processing multiple cells in parallel.

Customer impact

Customers receive ready-to-install cell packages, reducing on-site planning, personnel and resource needs, while enabling closer integration of assembly and service, including ongoing operations and cell replacement.

Source: thyssenkrupp nucera

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

12 August 2026
thyssenkrupp nucera doubles nine‑month order intake, halts SOEC mass‑production plan

Nearly doubled nine‑month order intake; wins Moeve 300‑MW contract with service package; discontinues SOEC mass‑production, incurring ~€30m one‑time EBIT hit and updating FY26 outlook.

16 September 2026
Moeve brings Hy24 and COFIDES into Onuba phase of Andalusian Green Hydrogen Valley

First phase includes a 300 MW electrolyser (>€1bn capex), ~45,000 t H2/yr and ~250,000 t CO2 avoided; received €304m public funding and reached FID.

9 June 2026
Moeve 2025 Environmental Statement for La Rábida and Palos

Annual report shows €33.8m+ invested in environmental upgrades, 100% renewable power in 2025, major waste recovery and water-use cuts, plus EU funding for green hydrogen project.

18 March 2026
thyssenkrupp nucera to supply 300 MW electrolyzers for Moeve’s Onuba green-hydrogen plant

First phase in Huelva, Spain, will yield ~45,000 t/yr green H2; FID taken Mar 2026. Expected CO2 savings ~250,000 t/yr; part of a scalable Andalusian Green Hydrogen Valley linking to EU industry