Técnicas Reunidas to supply hydrogen reformers for Dangote’s Gode fertilizer complex

Key highlights
  • Dangote’s Gode fertilizer complex is planned to produce 3 million tonnes per year of urea using Ethiopia’s natural gas reserves.
  • Técnicas Reunidas was awarded the contract to supply two hydrogen production reformers with combined capacity of over 200,000 Nm³/h.
  • TR-Technical will handle design, procurement, manufacture and FOB supply, with delivery within a maximum of 18 months.
  • Topsoe is the technology licensor for the reformers, and the award follows Técnicas Reunidas’ recent engineering contract for a large green hydrogen plant in South Africa.

Contract scope

The Dangote Group awarded Técnicas Reunidas the contract to supply two hydrogen production reformers for the ammonia and urea fertilizer complex being developed in Gode, Somali region, Ethiopia. The scope covers design, procurement, manufacture and FOB supply.

Project and capacities

The Gode plant will use Ethiopia’s natural gas to produce ammonia and urea and is planned to have an annual urea capacity of 3 million tonnes. The two reformers will provide hydrogen at a combined production capacity of over 200,000 Nm³/h.

Suppliers and timing

TR-Technical, the Técnicas Reunidas division for heat-transfer equipment, will supply the reformers within a maximum of 18 months. Topsoe will act as technology licensor for the reformers. The award follows a recent Técnicas Reunidas engineering contract for a large green hydrogen plant in South Africa.

Source: Técnicas Reunidas

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

27 January 2026
Topsoe Supports Saudi Arabia's Green Ammonia Project

Topsoe's technology will enable green ammonia production in Saudi Arabia, reducing CO2 emissions by 1.7 million tons annually, with operations expected to start in 2030.

27 January 2026
Topsoe Supports Saudi Arabia's Green Ammonia Project

Topsoe's technology will enable green ammonia production in Saudi Arabia, reducing CO2 emissions by 1.7 million tons annually, with operations expected to start in 2030.

19 October 2026
Técnicas Reunidas wins EPCM contract for Coastal GasLink Phase 2

EPCM award for Coastal GasLink Phase 2 covers detailed engineering, procurement and construction management for five compressor stations in BC; contract >€200m with 4+ year execution.

30 July 2026
Técnicas Reunidas consolidates growth as Middle East and data‑centre power lift results

Q2 EBIT €73m (5% margin); H1 orders €6bn and backlog €14bn; >€5bn UAE sole‑contract win; Greenlight gas+CCS plant to power a META data centre; guidance above €6.5bn revenue.

10 July 2026
Técnicas Reunidas wins 932 MW Alberta power plant for META data centre

Consortium to build a 932 MW combined‑cycle gas plant in Alberta to power META’s large AI data centre; plant will include carbon capture and can be doubled to 1,864 MW.