Siemens Gamesa launches wind tower made with lower-carbon steel

Key highlights
  • GreenerTower steel plates are designed to cut emissions by at least 63% compared with conventional steel.
  • RWE and Siemens Gamesa will use 36 towers at the 1,000-MW Thor offshore wind project in Denmark.
  • Thor is planned to have 72 SG 14-236 DD turbines, with installation starting in 2026.
  • Salzgitter AG’s Ilsenburger Grobblech is the first qualified steel supplier.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
RWE Thor 1.1 GW Offshore Wind Farm, Denmark · Denmark
Commissioning & Start-up
2018-06
2022-10
~2023
2024-11
2026-03-04
Operational / Completed · expected date for subscribers

Lower-carbon tower steel

Siemens Gamesa has launched the GreenerTower, which uses steel plates with at least 63% lower CO₂ emissions than conventional steel. The company’s qualification process sets a maximum of 0.7 tonnes of CO₂-equivalent emissions per tonne of steel, while requiring the same properties and quality. Towers are approximately 80% steel plates.

Greener steel production involves using more scrap, less energy-intensive processes and more renewable energy. Siemens Gamesa says steel manufacturing emits an average of 1.91 tonnes of CO₂ per tonne of steel.

First project and supplier

RWE and Siemens Gamesa have agreed to install 36 GreenerTowers at the 1,000-MW Thor offshore wind project in Denmark. The project is planned to include 72 SG 14-236 DD turbines, with installation starting in 2026. GreenerTower will be available for onshore and offshore projects scheduled for installation from 2024 onward.

Salzgitter AG, through its heavy plate mill Ilsenburger Grobblech GmbH, is the first qualified supplier. Its qualification has also received third-party certification.

Emissions context

Tower production accounts for more than one-third of wind-turbine-related CO₂ emissions, according to Siemens Gamesa.

Source: Siemens Energy

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

17 March 2026
Thor Offshore Wind Farm Begins Power Generation, Reports RWE

Thor offshore wind farm starts feeding electricity into Denmark's grid, aiming to power over one million homes by 2027 with sustainable features and local job creation.

26 January 2026
Danish Energy Agency Approves RWE's Thor Offshore Wind Farm

Thor offshore wind farm receives a 30-year production license. Construction is on track, with turbine installation starting this spring. Completion expected in 2027 to power 1M Danish homes.

9 July 2026
Salzgitter AG to acquire 100% of Hüttenwerke Krupp Mannesmann (HKM)

Acquire Duisburg steelworks, convert site to electric-arc furnace, cut workforce from ~3,000 to ~1,000 and aim for ~90% CO2 reduction.

12 February 2026
thyssenkrupp Q1 2025/2026: Sales Down, EBIT Up, Forecast Confirmed

Order intake fell due to prior major contracts. Sales dropped 8%, but EBIT rose 10% via APEX program. Transformation progresses with strategic moves in various segments.

6 February 2026
Salzgitter AG to Become Sole Shareholder of HKM from June 2026

Agreement reached for share transfer; slab supply to thyssenkrupp Steel secured until 2028. Approval from governing bodies and Vallourec S.A. required.