Fred. Olsen Windcarrier is a Norway-based offshore wind installation and marine services company within the Fred. Olsen group. It specializes in the transport and installation of offshore wind turbines and other large components for utility-scale wind farms.

Read more

The company operates a fleet of purpose-built self-elevating jack-up installation vessels and related support assets. Its services span heavy-lift installation, marine logistics, engineering, and project management from pre-assembly through commissioning and maintenance campaigns. Fred. Olsen Windcarrier works with wind farm developers, OEMs, and EPC contractors across European and other offshore wind markets, supporting the build-out of renewable power infrastructure for energy-intensive industries.

Projects Fred. Olsen Windcarrier is involved in

chemXplore tracks 1 project involving Fred. Olsen Windcarrier, of which one is active.

  1. none Announced / Concept
  2. none FEED / Pre-FID
  3. none FID / Sanctioned
  4. none Under Construction
  5. 1 project Commissioning & Start-up

1 more active project is in our database. See all 1 in chemXplore

Fred. Olsen Windcarrier in chemical industry news

11 May 2026
Ørsted and PGE start Baltica 2 offshore installation

First foundations installed for a 1.5 GW offshore wind farm. 111 monopiles (107 turbine, 4 substation) to be installed through Q4 2026; commissioning expected in 2027; 25-yr CfD.

17 March 2026
Thor Offshore Wind Farm Begins Power Generation, Reports RWE

Thor offshore wind farm starts feeding electricity into Denmark's grid, aiming to power over one million homes by 2027 with sustainable features and local job creation.

26 January 2026
Danish Energy Agency Approves RWE's Thor Offshore Wind Farm

Thor offshore wind farm receives a 30-year production license. Construction is on track, with turbine installation starting this spring. Completion expected in 2027 to power 1M Danish homes.

21 April 2023
Siemens Gamesa launches wind tower made with lower-carbon steel

The steel plates must meet a limit of 0.7 tonnes of CO₂-equivalent emissions per tonne, cutting emissions by at least 63% against conventional steel.