Heidelberg Materials Q3: RCO +9% and positive 2026 outlook confirmed

Key highlights
  • Revenue increased 10% to €6,413 million in Q3; result from current operations (RCO) rose 9% to €1,281 million.
  • Signed 7 October 2026 to acquire NCC AB Industry assets in Sweden and Norway (106 aggregates sites, 44 hot‑mix asphalt plants).
  • Completed 1 October 2026 acquisitions of Maas Group construction materials (43 quarries, 22 ready‑mix plants, five asphalt operations, one recycling site) and 70% of Cementos Inka (two grinding and two ready‑mix plants).
  • Transformation Accelerator will exceed a €500m target this year and is expanded to deliver an additional €300m of savings by end‑2028, split nearly equally across 2027 and 2028.
Related projects For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Heidelberg Materials Padeswood CCS Project (HyNet) · United Kingdom
Under Construction
2021-03
2024-02
2025-09-25
2025 Q4
—
Operational / Completed · expected date for subscribers
CI4C Catch4Climate Pure Oxyfuel Demo Plant, Mergelstetten · Germany
Operational / Completed
2019-12
2020-11
2022-06
2022-11
2026-05
2026-07-08
CI4C catch4climate Pure Oxyfuel R&D Plant at Mergelstetten · Germany
Operational / Completed
2019
2020-11
2022
2022-11
2025
2026-07-08
+ 1 more tracked in chemXplore

Third‑quarter performance

Revenue rose by €606 million or 10% to €6,413 million in Q3, while result from current operations (RCO) increased by €103 million or 9% to €1,281 million. Management attributes the improvement to stronger business in Europe, sustained growth in North America, active cost and price management, productivity gains and recovering demand.

Portfolio and acquisitions

Heidelberg Materials continued targeted portfolio optimisation. On 7 October 2026 it agreed to buy NCC AB’s Industry aggregates and asphalt activities in Sweden and Norway (106 aggregates sites, 44 hot‑mix asphalt plants). On 1 October 2026 it completed acquisitions of the Maas Group construction materials business (43 quarries, 22 ready‑mix plants, five asphalt operations, one recycling site) and a 70% stake in Cementos Inka (two grinding and two ready‑mix plants).

Cost programme and efficiency

The Transformation Accelerator Initiative has already produced significant savings and will exceed the €500 million target by year‑end. The initiative is being continued and expanded to achieve an additional €300 million in savings by end‑2028, realised nearly equally in 2027 and 2028. Structural actions in Europe include a focus on the clinker and cement network and the announced closure of the Ranville site in France.

Sustainability and capital allocation

Progress continues on carbon capture projects: Padeswood (UK) aims to capture ~95% of the plant’s CO₂ (~800,000 tonnes/year) with major plant sections due to arrive from April 2027, and the Mergelstetten R&D oxyfuel facility captured its first high‑purity CO₂ in July 2026. The company completed the third tranche of a €1.2 billion buyback on 1 October 2026 (total ~€448 million in the final tranche).

Outlook

The Managing Board confirms its 2026 guidance: RCO expected between €3.40 billion and €3.65 billion and ROIC to remain slightly above 10%. Specific net CO₂ emissions per tonne of cementitious material are expected to stay around the prior year’s level following the first‑time consolidation of Akçansa.

Source: Heidelberg Materials

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

16 September 2026
Heidelberg Materials to close Ranville cement plant

Closure of Ranville cement site after weak French demand; 87 employees affected; shift to lower‑clinker, higher‑value cement to cut CO₂; €650m invested in other French sites.

30 July 2026
Heidelberg Materials reports Q2 revenue €6.04bn and narrows 2026 RCO range

Revenue rose 6% to €6,044m and RCO to €1,086m. Strategic acquisitions in North America and Turkey; new 1.25 Mt kiln in France and Padeswood CCS on schedule.

9 July 2026
thyssenkrupp debuts CI4C Catch4Climate Pure Oxyfuel plant in Mergelstetten

Semi‑industrial demonstration replaces air with oxygen to raise flue‑gas CO₂ and enable near‑95% capture from clinker; dedicated 450 t/day kiln built with >€120m investment.

8 July 2026
CI4C inaugurates catch4climate Pure Oxyfuel R&D plant

World-first R&D site tests Pure Oxyfuel CO₂ capture at a Mergelstetten cement line to demonstrate energy- and cost-efficient capture and enable wider deployment.

25 September 2025
Heidelberg Materials Approves CCS Project at UK Cement Plant

The UK Government funds a CCS facility at Padeswood, capturing 800,000 tonnes of CO₂ annually, operational by 2029, boosting net-zero cement production and local jobs.