Gasunie repurposes 60-km pipeline to gather biomethane

Key highlights
  • 60-kilometre existing natural gas pipeline repurposed for biomethane collection through five municipalities.
  • Project links regional DSOs RENDO, Enexis and Coteq to the national transmission network operated by GTS.
  • Collected biomethane is routed to a GTS plant in Ommen where two new boosters raise pressure for injection to the national grid.
  • Biomethane production rose 14% last year; a planned blending obligation is expected to create steady demand and incentivise further investment.

Project overview

Gasunie Transport Services (GTS) has repurposed an existing 60-kilometre natural gas pipeline to serve as a gathering pipeline for biomethane. The line runs through Emmen, Coevorden, Hoogeveen, Hardenberg and Ommen, and reuse of the existing asset limited local construction impact.

Network connection and partners

The gathering pipeline connects regional distribution networks operated by RENDO, Enexis and Coteq to GTS’s national transmission network, enabling collection from regional production sites and transport to the national grid.

Capacity, boosting and market effects

Biomethane collected in the pipeline is transported to a GTS plant in Ommen, where two new biomethane boosters raise pressure for injection into the national network. Because biomethane production is year-round while demand is seasonal, the pipeline facilitates moving summer surpluses to demand centres and creates capacity for further production growth.

Production drivers and feedstocks

Biomethane is produced from organic waste streams such as food residues unfit for consumption, manure and sewage sludge via anaerobic digestion and, in future, gasification. Production in the Netherlands grew by 14% last year, and a forthcoming blending obligation is expected to provide steady demand and encourage investment in new plants.

Source: Gasunie

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

17 July 2026
Gasunie H1 2026: advancing hydrogen, CO₂, heat and LNG infrastructure

Opened a 32‑km Rotterdam hydrogen pipeline, progressed CO₂ and heat projects, boosted LNG capacity, and saw shifting gas flows with higher power‑sector demand.

6 March 2026
Gasunie 2025 Report: Advancing Resilient and Sustainable Energy Systems

Invested €1.2B in energy security and transition. Hydrogen, CO2 projects near completion. Net profit rose to €85M. Gas transport up, especially to power stations.

27 April 2025
Blending Obligation Boosts Perpetual Next's Green Gas Initiatives

The blending obligation mandates green gas in the grid by 2027, enhancing production opportunities and supporting national climate goals.

4 June 2026
Hydrogen value chain forming in North Sea Canal Area

Import terminals, LOHC and electrolysers advance; pipeline and local distribution are planned, but policy, financing and coordination still limit rollout.

9 July 2026
PwC study for Gasunie: CCS, low‑carbon hydrogen and hybrids are most cost‑effective for Dutch industry decarbonisation

CCS, low‑carbon hydrogen and hybrid electrification are the cheapest routes to cut industrial CO2 — timely CO2/H2 infrastructure is essential.