Gate terminal adds fourth 180,000 m³ LNG tank, boosting regasification to 20 bcm/y

Key highlights
  • Fourth LNG tank completed; commissioning scheduled for 1 October after a three-year construction period.
  • Tank holds 180,000 m³ of LNG and adds 4 billion m³/year regasification, taking Gate's total to 20 billion m³/year (Dutch market ≈30 billion m³/year).
  • Gate is a joint venture between Gasunie and Vopak that receives, stores and regasifies LNG for delivery via the gas transmission network.
  • After a Jan 2026 FID, Port of Rotterdam's Jetty 4 is under construction with small-scale loading and bunkering expected by end‑2028; Gate opened an unbinding EoI for Jetty 5 on 31 Aug 2026.
Related projects For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Gate Terminal 4th LNG Tank Expansion, Rotterdam · The Netherlands
Commissioning & Start-up
2023-08-23
2023-08-23
2023-09
2026-10-01
—
Port of Rotterdam Jetty 4 LNG Breakbulk Jetty at Gate Terminal · The Netherlands
Under Construction
2024-03
2025
2026-01-13
2026-02
—
Operational / Completed · expected date for subscribers

Completion and commissioning

Construction of the fourth LNG storage tank at Gate terminal on the Maasvlakte in Rotterdam has been completed as scheduled. The new tank will be commissioned as of 1 October after a three-year construction period.

Capacity and market context

The tank has a storage capacity of 180,000 cubic meters of LNG and increases the terminal's regasification capacity by 4 billion cubic meters per year, bringing Gate's total to 20 billion cubic meters per year. By comparison, the total Dutch gas market has a volume of approximately 30 billion cubic meters per year. The decision to build the additional tank was made partly in response to the 2022 energy crisis.

Infrastructure and next steps

Following a final investment decision in January 2026, construction of Jetty 4 by the Port of Rotterdam is underway and is expected to start small-scale ship loading and bunkering operations by the end of 2028. Gate launched an unbinding Expression of Interest on 31 August 2026 to allow market parties to indicate interest in future loading capacity for an intended Jetty 5.

Role and ownership

Gate is a joint venture between Gasunie and Vopak. The terminal receives LNG by ship, stores it in liquid form, and makes it suitable for delivery via the gas transmission network to users in the Netherlands and surrounding countries, increasing the capacity to supply LNG from different parts of the world.

Source: Gasunie

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

17 July 2026
Gasunie H1 2026: advancing hydrogen, CO₂, heat and LNG infrastructure

Opened a 32‑km Rotterdam hydrogen pipeline, progressed CO₂ and heat projects, boosted LNG capacity, and saw shifting gas flows with higher power‑sector demand.

30 September 2026
Uniper and Biotrend assess Turkish biomethane for European markets

Assessing conversion of Turkish waste-based biogas plants to biomethane for export to the EU via existing gas grids.

16 July 2026
Gasunie positions the Netherlands as Europe’s CO₂ hub

Five connected CCS projects (Porthos, Aramis, CO₂next, DRC, DSC) will capture, transport and store CO₂ under the North Sea and link industry across the Netherlands, Belgium and Germany.

1 June 2026
Vopak and Gasunie take conditional FID to extend EemsEnergyTerminal

Conditional FID approved for extension of EemsEnergyTerminal, advancing LNG infrastructure; final FID pending permits. Customer contracts secured for LNG supply 2028–2036.

9 April 2026
Gasunie and Fluxys sign JDA to link Dutch and Belgian hydrogen networks

Targeted by ~2030: cross-border bidirectional hydrogen connection using repurposed gas pipelines (Zandvliet node) to connect major ports/industrial clusters and enable integrated NW-European trade