Hydrogen Pipeline Milestone in Rotterdam by Hynetwork

Key highlights
  • The final weld of a 32-km hydrogen pipeline in Rotterdam was completed in mid-August.
  • Construction started in April 2024, navigating a complex landscape of infrastructure.
  • The pipeline will connect the Port of Rotterdam to Germany, Belgium, and the Netherlands.
  • Next steps include testing, pre-commissioning, and commissioning.

Milestone Achieved

The final weld of a 32-kilometer hydrogen pipeline in Rotterdam was completed in mid-August, marking a significant milestone. This pipeline is the first section of the national hydrogen network, setting the stage for the Port of Rotterdam to become a major energy gateway for Europe, connecting to Germany, Belgium, and the rest of the Netherlands.

Construction Challenges

Construction began in April 2024 after several years of preparation. The route through the Rotterdam port area had to navigate a dense landscape of roads, railways, waterways, and hundreds of existing pipes and cables. At intersections, the pipeline sometimes had to pass beneath 20 or more operational pipes and cables, making it a complex operation.

Next Steps

With the welding complete, the next phase involves testing, pre-commissioning, commissioning, and preparing the pipeline for operation. These steps are crucial to ensure the pipeline's readiness and integration into the broader energy network.

Source: Gasunie

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

9 April 2026
Gasunie and Fluxys sign JDA to link Dutch and Belgian hydrogen networks

Targeted by ~2030: cross-border bidirectional hydrogen connection using repurposed gas pipelines (Zandvliet node) to connect major ports/industrial clusters and enable integrated NW-European trade

8 January 2026
Hydrogen Pipeline Key to Energy Transition at Port of Rotterdam

The hydrogen pipeline's completion is vital for sustainable industry, linking producers and consumers, and supporting future growth in Rotterdam's port area.

24 September 2026
Dutch minister seeks short-term amortisation decision to unlock national hydrogen network

Government will finalise a financing approach this year to give investors certainty and keep hydrogen transport tariffs affordable as market develops.

18 September 2026
Hynetwork (Gasunie) opens North Sea Canal Area hydrogen network draft for public review

Draft project decision, EIA and permits open for comment 18 Sep–29 Oct 2026; route crosses Beverwijk, Velsen, Zaanstad, Haarlemmermeer and Amsterdam.

4 June 2026
Hydrogen value chain forming in North Sea Canal Area

Import terminals, LOHC and electrolysers advance; pipeline and local distribution are planned, but policy, financing and coordination still limit rollout.