Chandra Asri Group advances CA‑EDC plant into jetty and storage tank construction

Key highlights
  • Project is 66% complete and has entered the jetty and storage tank development phase to support logistics and distribution.
  • Plant initial annual capacity: 827,000 tonnes caustic soda and 500,000 tonnes ethylene dichloride (EDC).
  • Caustic soda output could substitute up to ~827,000 tpa of imports, valued at about USD 293 million (IDR 4.9 trillion); EDC exports could generate up to USD 300 million (≈IDR 5 trillion) annually.
  • Project engaged ~3,000 construction workers to date and is expected to create around 250 jobs on start‑up, with operations targeted in Q1 2027; local UMKM are being involved in the supply chain.

Project progress

The CA‑EDC plant has reached 66% completion and moved into the construction phase for key logistics infrastructure, specifically a jetty and storage tanks. This infrastructure is intended to support distribution, storage and logistics management for chlor alkali and ethylene dichloride products and to improve connectivity across the national and regional chemical supply chain.

Production capacity and market impact

In its initial operational phase the facility is targeted to produce 827,000 tonnes per year of caustic soda and 500,000 tonnes per year of EDC. Caustic soda production is expected to reduce Indonesia's import dependence and could substitute up to approximately 827,000 tpa of imports, with an estimated value of USD 293 million (IDR 4.9 trillion). EDC output will be directed to export markets, with potential foreign exchange earnings of up to USD 300 million (≈IDR 5 trillion) per year.

Economic and social impact

The development has engaged about 3,000 workers during construction and is expected to create roughly 250 jobs when fully operational, targeted in the first quarter of 2027. The project also involves local UMKM for various supply chain and operational needs, aiming to strengthen the surrounding industrial ecosystem and local economic activity.

Source: comsite-s3.s3.ap-southeast-3.amazonaws.com

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

29 September 2026
Chandra Asri CA‑EDC project 80% complete as main equipment installation begins

USD>800M CA‑EDC plant at 80% completion; main equipment being installed; start planned for 2027; capacities 827 kt caustic soda and 500 kt EDC with significant import substitution and export potential.

3 March 2026
Danantara, INA and Chandra Asri back USD 800m CA‑EDC plant in Cilegon

Joint investment will fund local Caustic Soda and EDC capacity to cut import reliance and support downstream industrialisation.

20 February 2026
Chandra Asri Group reaches 50% completion of CA‑EDC plant

Chlor‑alkali/EDC plant hits 50% construction and aims for commercial start in Q1 2027; capacity 827,000 t caustic soda and 500,000 t EDC with import substitution and export value.

19 March 2025
Chandra Asri Group to build CA-EDC plant in Cilegon

IDR 15 trillion CA-EDC complex with 400kt caustic (solid)/827kt liquid and 500kt EDC yearly; 3,250 jobs; completion targeted for 2027; 2025 capex USD 350–400m.

4 March 2025
Chandra Asri Group to build CA‑EDC plant in Cilegon, Banten

Designated a National Strategic Project, the CA‑EDC complex will cost IDR 15 trillion and produce 400,000 t caustic soda and 500,000 t EDC per year.