VIDA bioenergy starts biomethane injection at Wormslade

Key highlights
  • Wormslade has begun injecting biomethane into the UK gas grid, marking the start of commercial operations.
  • The plant is designed to process ~46,000 tonnes of feedstock annually and produce ~68 GWh of biomethane per year, enough to heat over 5,000 homes.
  • Wormslade will generate ~70,000 tonnes of nutrient-rich digestate annually to be returned to agriculture as organic fertiliser.
  • VIDA plans to ramp production to full operating capacity and complete remaining commissioning by October 2026.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
VIDA bioenergy Wormslade Biomethane Plant · United Kingdom
Commissioning & Start-up
2025-02-04
2025-02-04
2026-07
2026-10

Project milestone

VIDA bioenergy’s Wormslade biogas facility has successfully injected biomethane into the UK gas grid and moved into commercial operations, allowing the plant to begin supplying renewable biomethane to local energy networks.

Capacity and outputs

The facility is designed to process approximately 46,000 tonnes of feedstock each year and produce around 68 GWh of renewable biomethane annually — stated as sufficient to heat more than 5,000 homes. It will also produce about 70,000 tonnes of nutrient-rich digestate per year for use as organic fertiliser in agriculture.

Timeline and next steps

VIDA will ramp up biomethane production toward full operating capacity and complete commissioning of remaining auxiliary systems before final performance testing and handover to operations. Full capacity is expected by October 2026.

Strategic context

Wormslade is VIDA’s fourth operational biogas facility and fits the company’s wider strategy to expand renewable gas production across Europe. Cadent noted the potential for significant growth in UK biomethane, targeting a five-fold increase in production over the next decade.

Source: VIDA bioenergy

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

7 May 2025
VIDA bioenergy scales RNG and biogas across Europe

New VTTI subsidiary launched Jan 2025 to scale biomethane, liquid CO₂ and organic fertilisers; Wormslade due mid‑2026; projects in UK, Netherlands and Poland.

2 July 2026
VIDA bioenergy Bernheze plant begins biomethane production

Bernheze plant starts injecting biomethane into the Dutch grid, ramping to 8 million m³/year and processing ~72,000 t/year of agricultural feedstock.

27 January 2026
VIDA bioenergy advances Wormslade biomethane AD site

Wormslade AD site has civil works largely complete and gas domes installed; it aims to produce biomethane to heat about 5,000 homes, with gas processing in Q2 2026 and production-ready in Q3 2026.

9 December 2025
VIDA bioenergy commissions liquid CO₂ plant in Glentham, UK

First biogenic CO₂ recovery and liquefaction unit now operational at Glentham; the site also produces 60 GWh/year of biomethane injected into the UK transmission system.