VIDA bioenergy

The Netherlandsvidabioenergy.com

VIDA bioenergy is a European biomethane producer and fully owned subsidiary of VTTI. Launched as an independent entity in January 2025, the company develops, builds, and operates facilities that convert sustainable biomass into renewable natural gas. Operations and projects are underway in the Netherlands, the United Kingdom, and Poland.

Its products include biomethane for grid injection, biogenic CO2, and organic fertilizer, supporting decarbonization of buildings, heavy transport, and industrial processes. The company maintains an active status with facilities such as those in Tilburg and Bernheze (Netherlands) and Glentham (UK).

Projects VIDA bioenergy is involved in

chemXplore tracks 4 projects involving VIDA bioenergy, of which 2 are active.

VIDA bioenergy's role on them: Owner, Operator, and Developer.

1 FEED / Pre-FID 1 Commissioning & Start-up

2 new construction.

Expected to start operating, per year; 1 of the active projects carry no start-up date yet.

What moved recently
  • July 2026 VIDA bioenergy Bernheze biomethane revamp, Netherlands · Operational / Completed
  • July 2026 VIDA bioenergy Wormslade Biomethane Plant · Commissioning & Start-up · United Kingdom

Contractors, licensors, and offtakers are recorded on 1 of these 2 projects For subscribers

Targeting: Methane (2), NPK - fertilizer (1)

Follow these projects in chemXplore →

Latest news on VIDA bioenergy

21 July 2026
VIDA bioenergy starts biomethane injection at Wormslade

Plant moves to commercial operations, supplying renewable biomethane to the UK gas grid and ramping to full capacity by October 2026.

2 July 2026
VIDA bioenergy Bernheze plant begins biomethane production

Bernheze plant starts injecting biomethane into the Dutch grid, ramping to 8 million m³/year and processing ~72,000 t/year of agricultural feedstock.

27 January 2026
VIDA bioenergy advances Wormslade biomethane AD site

Wormslade AD site has civil works largely complete and gas domes installed; it aims to produce biomethane to heat about 5,000 homes, with gas processing in Q2 2026 and production-ready in Q3 2026.

9 December 2025
VIDA bioenergy commissions liquid CO₂ plant in Glentham, UK

First biogenic CO₂ recovery and liquefaction unit now operational at Glentham; the site also produces 60 GWh/year of biomethane injected into the UK transmission system.

7 May 2025
VIDA bioenergy scales RNG and biogas across Europe

New VTTI subsidiary launched Jan 2025 to scale biomethane, liquid CO₂ and organic fertilisers; Wormslade due mid‑2026; projects in UK, Netherlands and Poland.

Where its projects are

By country, the most active first.