Uniper to invest €120m in Bierwang gas storage upgrade

Key highlights
  • Uniper plans to reduce the time needed to fill the facility by about 30% by 2030.
  • Expansion of existing wells is expected to add around 40 million cubic metres of storage capacity.
  • A 10 MW electric compressor will replace two gas-engine-driven compressors.
  • Pure hydrogen injected in the HyStorage project is scheduled for withdrawal in January 2027.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Uniper Bierwang2030 Gas Storage Modernisation · Germany
Announced / Concept
2026-11-25
—
—
—
—
Operational / Completed · expected date for subscribers

Upgrade targets higher performance

Uniper plans to invest around €120 million in the Bierwang gas storage facility. By 2030, it aims to cut the time needed to fill the facility by about 30% and increase maximum withdrawal capacity. Expanding existing wells is expected to add around 40 million cubic metres of storage volume.

A new electric compressor unit with a capacity of around 10 MW will replace two gas-engine-driven compressors. It is designed for potential future use with hydrogen.

Lower emissions

The programme is expected to reduce annual site emissions by around 11,000 tonnes of CO₂ and 64 tonnes of methane, more than halving current site-related emissions. Measures include the electric compressor and a recompression unit.

Hydrogen storage research

Under the HyStorage project, Uniper is investigating hydrogen storage in porous rock formations. Pure hydrogen has been injected for the first time in the project’s fifth test phase. After around three months in a smaller, isolated storage horizon, it is scheduled to be withdrawn in January 2027 for analysis. The findings are intended to inform German and European storage systems.

Source: Uniper

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

16 July 2026
Uniper supplies Q1 Energie AG with bio‑LNG

Initial delivery expands bio‑LNG availability for heavy road transport; biomethane is liquefied at Gate Rotterdam, shipped in ISO tanks to Germany and distributed to filling stations.

17 November 2026
Hycamite: Germany sets out €1.5bn hydrogen support package

The measures cover hydrogen for industry and power generation, alongside infrastructure investment, import plans and demand incentives for lower-carbon materials.

4 November 2026
EU Innovation Fund backs three InnoEnergy portfolio companies

Projects target low‑carbon iron feedstock, a 5 GW European solar cell and module factory, and biogenic CO₂-to-e‑methane systems, advancing to industrial-scale deployment.

3 November 2026
Gasunie repurposes 60-km pipeline to gather biomethane

A 60-km existing natural gas line has been converted to collect regional biomethane and feed it into the national transmission network, linking three DSOs and two pressure boosters at Ommen.

29 September 2026
GEN‑H to build 200–300 MW zero‑emission balancing plant in Kotka using Hycamite methane pyrolysis