Equinor: Troll Phase 3 Stage 2 boosts gas supply to Troll A

Key highlights
  • Production from Troll Phase 3 stage 2 started on 22 August.
  • The project accelerates production of about 55 billion standard cubic metres from the Troll West reservoir.
  • Start-up was achieved ahead of schedule and several hundred million Norwegian kroner below the original NOK 12.3 billion estimate.
  • An eight-well campaign was completed in five and a half months, 25% faster than planned; a 28 km, 36-inch pipeline was installed by Pioneering Spirit.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Equinor Troll Phase 3 Stage 2 Gas Expansion · Norway
Operational / Completed
2024-05
2024
2026-08-22

Production start

Production from Troll Phase 3 stage 2 began on 22 August, supplying additional gas to the Troll A platform and supporting deliveries through the Kollsnes processing plant, which marks its 30th anniversary this year.

Volumes and timing

The project accelerates production of about 55 billion standard cubic metres from the Troll West reservoir. Phase 3 stage 2 came on stream just over two years after the partnership’s investment decision.

Execution and cost performance

The development reused subsea facilities and standardised solutions from the 2021 Phase 3 project to reduce execution time and costs. The eight-well drilling campaign was completed in five and a half months by the Deepsea Aberdeen rig—25% faster than planned—and the start-up was delivered ahead of schedule and several hundred million Norwegian kroner below the original NOK 12.3 billion estimate.

Infrastructure and economic impact

Key contractors and suppliers included OneSubsea, Aker Solutions, Ocean Installer, SLB, Baker Hughes, Pioneering Spirit and Randaberg Industries; work covered templates, manifolds, an extended umbilical, MEG line extension and a 28-kilometre, 36-inch pipeline. The project helps sustain gas deliveries to Europe, local jobs and state revenues, with more than 90% of Troll profits passing to the Norwegian state via taxes and Petoro.

Source: Equinor

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

19 June 2026
Equinor-led TWIN subsea tieback to boost Troll gas exports

Subsea tieback will add about 11 billion Sm3 of gas, cost just over NOK 4 billion and target production start as early as 2028.

7 July 2026
Equinor awards NOK 6bn contracts for four subsea projects on Norwegian shelf

Contracts are part of a coordinated first subsea wave to speed delivery and cut costs by standardising equipment and processes across multiple developments.

26 August 2025
ORLEN Boosts Norwegian Gas Output by 500 Million Cubic Meters

The Ormen Lange field's third phase uses subsea compressors to enhance gas production, improve efficiency, and reduce emissions, increasing recovery rates from 75% to 85%.

23 September 2025
Equinor Boosts LNG Production in Europe

Askeladd Vest field starts production, enhancing LNG output at Melkøya. It supports Hammerfest LNG's full capacity until 2028, contributing 2% to EU's gas needs.

15 June 2026
Equinor advances Johan Sverdrup phase 4 subsea development

Appraisal wells confirmed 20–30 million boe in Tonjer and Geitungen; planned subsea tie-back to maintain Johan Sverdrup production with possible start-up in 2029.