Perpetual Next names JPB Logistics for Farmsum biomethanol storage

Key highlights
  • Delfzijl (Farmsum) biomethanol plant being developed with a production capacity of 220,000 tons per year.
  • Intended storage capacity of 21,000 to 35,000 gross m³, depending on final configuration.
  • Logistics concept based on incoming pipelines and outgoing inland shipping via dedicated pipes, with truck loading/unloading as backup.
  • Collaboration is conditional on Perpetual Next's final investment decision, successful project execution and agreement on final commercial terms.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Perpetual Next Delfzijl DeltaTorr DeltaNor Biomethanol Project · The Netherlands
FEED / Pre-FID
2025-03
2025-07
—
2026
—
Operational / Completed · expected date for subscribers

Partnership

Perpetual Next has designated JPB Logistics as the preferred partner for storage and handling of biomethanol at its Farmsum (Delfzijl) plant. Under the intended collaboration, JPB will handle storage, transshipment and delivery of biomethanol to external customers.

Project and developer

The Delfzijl project is being developed by DeltaNor B.V., a wholly‑owned subsidiary of Perpetual Next, and DeltaNor is responsible for construction, financing, maintenance and operation of a biomethanol plant with a production capacity of 220,000 tons per year. The plant is part of Perpetual Next's programme to convert biogenic carbon streams into renewable products including biomethanol.

Storage and logistics

Current agreements set out the parties' intention to enter a definitive storage agreement targeting 21,000 to 35,000 gross m³ of capacity depending on the final configuration. The proposed logistics concept relies on incoming pipelines and outgoing inland shipping via dedicated pipes, with truck loading and unloading as a backup. JPB cites its terminal and berth infrastructure in Farmsum as capable of supporting the required safe and efficient logistics.

Conditions

The collaboration remains subject to conditions including Perpetual Next's final investment decision for the Delfzijl project, successful project execution and agreement on final commercial terms.

Source: Perpetual Next

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

5 October 2026
Perpetual Next and Lhyfe sign MoU to explore renewable hydrogen supply for DeltaNor biomethanol in Delfzijl

MoU to assess local renewable hydrogen supply for a planned Delfzijl biomethanol plant, targeting roughly 12,000 tonnes H2 per year to boost biomethanol yields.

14 September 2026
Perpetual Next appoints Bilfinger for Delfzijl biomethanol project

Appointment advances DeltaTorr/DeltaNor toward FID for a biomethanol plant converting biogenic residual streams, with up to €1 billion capital at stake.

3 September 2026
Perpetual Next and PreZero Netherlands to supply waste wood for biomethanol and biomethane

Low‑grade waste wood will be routed to Dutch biomethanol and biomethane plants to secure feedstock for scalable production.

21 May 2026
EemsGas secures €149.8m SDE++ operating subsidy for biomethane production

Project (>€100m) will build a demolition-wood gasification plant producing 18M m3/yr biomethane. Earlier €30m DEI+ grant. Construction 2027, operation 2029. Subsidy secures 15‑yr revenue

1 May 2026
Perpetual Next selects JPB Logistics for Delfzijl biomethanol storage

MoU to negotiate storage/handling for a 220,000 t/y biomethanol plant; planned tank capacity 21,000–35,000 m³; logistics via inbound pipeline, outbound barge, trucks as backup; final on FID.