RAG & bayernets: Cross-border hydrogen deliveries stalled by missing German certificates register

Key highlights
  • Pipeline deliveries from Austria to Germany began in September 2024 and have continued since.
  • At the end of January 2026 about 630 MWh of green hydrogen had been delivered, nearly six times the initial shipment.
  • Certificates of origin issued in Austria cannot be transferred because Germany lacks a compatible certificate register.
  • Project partners demand rapid implementation of a German register and faster cross‑border harmonization to enable market ramp‑up.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
RAG Austria & bayernets H2 Cross Border Project · Austria
Operational / Completed
2021
2024-09

Project scope and partners

Launched in 2021 by RAG Austria AG and bayernets GmbH, the H2 cross border project covers the hydrogen value chain from production via storage and transport to the end customer. MEGGLE Group is the buyer and Shell Energy Deutschland GmbH is a project partner.

Production and deliveries

RAG produces green hydrogen by water electrolysis with TÜV Süd certification, blends it into Austria's natural gas network and transfers it to bayernets' transport network in Burghausen for onward delivery to MEGGLE. Deliveries began in September 2024 and by the end of January 2026 reached around 630 MWh, nearly sextupling the initial volume.

Regulatory obstacle: certificates of origin

Although RAG and MEGGLE are registered in Austria's certificates database operated by E‑Control, Austrian certificates cannot be transferred to Germany because a compatible German certificate of origin register is not yet operational. Certificates therefore remain on the Austrian account and cannot be credited to German recipients. An inquiry to the German Federal Environment Agency did not yield a binding 2026 commissioning confirmation.

Requested actions

The project partners call for rapid implementation of a German certificate register, accelerated harmonization between Austria and neighboring countries, and shorter administrative paths to enable cross‑border tradability and unlock investments and scaling.

Source: RAG Austria AG

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

8 July 2026
RAG Austria & Andritz break ground on 12.5 MW electrolyser to scale Gampern from 2.5 to 15 MW

Groundbreaking for a self‑financed 12.5 MW electrolyser at Gampern to scale green hydrogen capacity to 15 MW, storing summer solar for winter electricity and heat use.

9 December 2025
H2EU+Store: Feasibility study finds Western Ukraine suitable for RFNBO hydrogen exports

Existing pipeline links enable economical transport to Austria and southern Germany; technical planning has started for an initial ~9,000 t/yr export project.

1 July 2025
RAG Austria AG & ENERGIEALLIANZ Austria: green power for Gampern hydrogen plant

Three GWh/year of 100% Austrian renewable electricity will power electrolysis in Gampern from June 2025 through at least end‑2026, feeding a 4.2 GWh underground hydrogen store.

23 February 2026
thyssenkrupp Steel Supplies CO₂-Reduced Steel for BMW iX3 Production

bluemint® Steel, a CO₂-reduced product, will be used in BMW iX3's outer panels and battery housing, enhancing sustainability and meeting high quality standards.

23 February 2026
thyssenkrupp Steel to Supply CO₂-Reduced Steel for BMW iX3 Production

bluemint® recycled steel, with high recycled content and CO₂ savings, will be used in BMW iX3's outer panels and battery housing, meeting quality and safety standards without process changes.