H2EU+Store: Feasibility study finds Western Ukraine suitable for RFNBO hydrogen exports

Key highlights
  • The study finds green, RFNBO-compliant hydrogen can be produced at scale in Western Ukraine at competitive costs.
  • Pipeline transport to Austria and southern Germany via Slovakia is feasible and is the most cost-effective option.
  • Lviv and Ivano-Frankivsk oblasts are identified as high-potential production locations due to wind, PV and water availability.
  • Technical planning for a first export project is underway with a secured land area in Lviv Oblast and an initial target of ~9,000 t/year.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
RAG Austria H2EU+Store Phase 1 green H2 plant, Lviv Oblast · Ukraine
FEED / Pre-FID
2025-04
2025-12
FID / Sanctioned · expected date for subscribers
—
—
Operational / Completed · expected date for subscribers

Scope and headline finding

The H2EU+Store feasibility study examined the full hydrogen value chain (upstream production, midstream transport, and customer demand) and concludes that green, RFNBO-compliant hydrogen can be produced in Western Ukraine at large scale and competitive prices and transported to Central European markets via existing infrastructure.

Resource and transport assessment

Western Ukraine — notably the Lviv and Ivano-Frankivsk oblasts — offers strong wind and PV resources, sufficient water availability and an existing transnational gas pipeline network. The study identifies pipeline-based transport as the most cost-effective option and highlights direct connections via Slovakia to Austria and southern Germany, positioning the region as a potential element of the European Hydrogen Backbone's East Import Corridor.

Demand, initial project and next steps

The study matches production potential with demand clusters such as Linz (Upper Austria) and the ChemDelta Bavaria in southern Germany, which require long-term offtake. Project teams have begun technical planning for an initial hydrogen production project for export, with a secured land area in Lviv Oblast and an expected first-step output of about 9,000 tonnes per year. The feasibility study is presented as the basis for developing production capacities in Western Ukraine and integrating them into the East Corridor to support market ramp-up.

Source: RAG Austria AG

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

8 July 2026
RAG Austria & Andritz break ground on 12.5 MW electrolyser to scale Gampern from 2.5 to 15 MW

Groundbreaking for a self‑financed 12.5 MW electrolyser at Gampern to scale green hydrogen capacity to 15 MW, storing summer solar for winter electricity and heat use.

4 February 2026
RAG & bayernets: Cross-border hydrogen deliveries stalled by missing German certificates register

Pipeline hydrogen deliveries from Austria to Germany reached ~630 MWh, but cross-border transfer of certificates of origin is blocked by the absence of a German register.

1 July 2025
RAG Austria AG & ENERGIEALLIANZ Austria: green power for Gampern hydrogen plant

Three GWh/year of 100% Austrian renewable electricity will power electrolysis in Gampern from June 2025 through at least end‑2026, feeding a 4.2 GWh underground hydrogen store.