Eni commissions 120 MW gas plant in Kazakhstan’s Mangystau hybrid project

Key highlights
  • The 247 MW project is being developed in Kazakhstan’s Mangystau Region by Eni, KazMunayGas and Plenitude.
  • The 120 MW gas plant was commissioned after 12 months of construction, involving 3 million man-hours without a lost-time injury.
  • The 50 MW solar plant was commissioned in September 2025; the gas plant reached first industrial electricity in July 2026.
  • Construction of the 77 MW wind plant is next, with commercial operations scheduled to begin in 2027.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Eni KazMunayGas Mangystau Hybrid Power Plant · Kazakhstan
Commissioning & Start-up
2023-06-08
2024-07-16
2025-09-27
Operational / Completed · expected date for subscribers

Project commissioning

Eni has commissioned a 120 MW gas power plant in Kazakhstan’s Mangystau Region. It is part of the 247 MW Mangystau Hybrid Power Plant Project, developed with KazMunayGas and Plenitude. The project integrates solar and gas generation, with wind power planned as a later phase, to supply power to KazMunayGas subsidiaries in the region.

Construction and commissioning took 12 months and involved 3 million man-hours without a lost-time injury. The plant reached first industrial electricity in July 2026 and is ready for operation by a KazMunayGas affiliate.

Remaining development

The project’s 50 MW solar plant was commissioned in September 2025. Work will now focus on a 77 MW wind plant. Most field civil works are expected to be completed by 2026, allowing installation of the first wind turbines. Commercial operations are scheduled to start in 2027, completing the hybrid configuration.

Source: Eni

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time. See our Privacy Policy.

Related articles

22 July 2026
Eni and KazMunayGas: first electricity from 120 MW gas unit at Mangystau hybrid plant

First industrial electricity from the 120 MW gas unit at the 247 MW Mangystau hybrid plant; integrates solar, gas and planned wind to decarbonize regional supply.

27 September 2025
Plenitude Commissions 50 MW Solar Plant in Kazakhstan

The 50 MW solar plant in Kazakhstan is part of a 247 MW hybrid project, integrating solar, wind, and gas to support energy transition and local economic growth.

11 November 2026
Eni confirms £11bn UK investment through 2030

Around two-thirds of the planned spending is allocated to lower-carbon sectors, including carbon capture, offshore wind and fusion.

23 October 2026
Eni boosts shareholder returns and upgrades 2026 outlook

Proforma gearing at a historic low of 9% and adjusted CFFO lifted to €16.5bn; underlying E&P output +7% to 1.83 mln boe/d. Strategic deals include Junin 5 relaunch and asset monetisations.

1 October 2026
Eni and Ares complete Plenitude capital restructure and joint governance

Non‑proportional €1.56bn capital increase sets pre‑money equity at €10.75bn; deconsolidation under joint control; board reconfigured with nine members and qualified‑majority voting on material matters.