Eni and KazMunayGas: first electricity from 120 MW gas unit at Mangystau hybrid plant

Key highlights
  • First Industrial Electricity was produced from the 120 MW Gas Power Plant in July 2026.
  • The Mangystau Hybrid Power Plant totals 247 MW and integrates solar, gas and planned wind capacity to supply KazMunayGas subsidiaries.
  • A 50 MW Solar Power Plant was commissioned in September 2025.
  • Project execution recorded over 2 million man‑hours without a Lost Time Injury; the gas plant is due for final commissioning in Q3 2026 and a 77 MW wind plant is planned to enter operation in 2027.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Eni KazMunayGas Mangystau Hybrid Power Plant · Kazakhstan
Commissioning & Start-up
2024-01-18
2024-07-16
2026 Q3
Operational / Completed · expected date for subscribers

Milestone achieved

Eni and KazMunayGas, together with Eni’s subsidiary Plenitude, report First Industrial Electricity from the 120 MW Gas Power Plant, a core element of the 247 MW Mangystau Hybrid Power Plant in the Mangystau Region of Kazakhstan. The facility is positioned as a large‑scale hybrid installation combining solar, gas and planned wind generation to provide decarbonized and reliable electricity to KazMunayGas subsidiaries in the region.

Execution and safety

From the start of construction to first electricity, the project recorded more than 2 million man‑hours without a Lost Time Injury, cited as evidence of strong execution, safety performance and coordination with local stakeholders during delivery of complex energy infrastructure.

Phased development and next steps

The project follows a phased approach: the 50 MW Solar Power Plant was commissioned in September 2025; the gas unit delivered first electricity in July 2026 and is scheduled for final commissioning within Q3 2026; the remaining 77 MW Wind Power Plant is planned to enter operation in 2027, which will complete the hybrid configuration.

Source: Eni

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

27 September 2025
Plenitude Commissions 50 MW Solar Plant in Kazakhstan

The 50 MW solar plant in Kazakhstan is part of a 247 MW hybrid project, integrating solar, wind, and gas to support energy transition and local economic growth.

1 October 2026
Eni and Ares complete Plenitude capital restructure and joint governance

Non‑proportional €1.56bn capital increase sets pre‑money equity at €10.75bn; deconsolidation under joint control; board reconfigured with nine members and qualified‑majority voting on material matters.

29 July 2026
Eni second-quarter 2026 results and updated capital plan

Double-digit underlying production growth, new JV and project FIDs, entry into critical minerals, and a larger share buyback with slightly higher 2026 production guidance.

23 July 2026
Enilive to acquire OIL! service-station network from Prax

Adds about 320 stations across Germany, Denmark, Austria and Switzerland; sites to be integrated progressively and will offer HVO biofuel, fast EV charging and convenience formats; subject to approvals.

16 June 2026
Eni and Hera launch Ravenna Environmental Hub

26-hectare Ca’ Ponticelle site repurposed for circular-economy hub with waste pretreatment, soil biorecovery, 6 MWp PV and experimental vanadium flow battery.