EIB lends KGHM €400 million for copper production and upgrades
- The EIB agreed a PLN 1.7 billion loan, equivalent to about €400 million, with KGHM.
- The financing supports investments valued at PLN 2.6 billion, including a new shaft due for completion in 2029.
- The GG-1 shaft is planned to reach nearly 1.4 kilometres underground.
- Funding also covers underground conveyors and electrorefining technology at a KGHM smelter.
Financing and investment scope
The European Investment Bank agreed a PLN 1.7 billion loan, equivalent to about €400 million, with Poland’s KGHM. The financing supports the company’s long-term investment programme, with supported investments totalling PLN 2.6 billion. It will fund access to deeper copper deposits, improvements to underground transport and modernised processing technology.
Projects and production
Financing will support construction of KGHM’s GG-1 shaft, scheduled for completion in 2029. At nearly 1.4 kilometres deep, the shaft is intended to improve access to deposits and will include ventilation and cooling systems. The loan also covers underground conveyors for less-polluting ore transport and installation of an electrorefining technology at a KGHM smelter.
Role in European copper supply
KGHM, headquartered in south-western Poland, accounts for around half of the EU’s primary copper production. Its operations cover mining, ore processing, smelting, refining and wire-rod production. The EIB said the financing is backed in part by an InvestEU guarantee and falls under its TechEU initiative.
Source: EIB