thyssenkrupp Uhde Completes Hydrogen Recovery Unit at Fertiglobe UAE Plant

Key highlights
  • The hydrogen recovery unit increases ammonia production by 6% and reduces CO2 emissions.
  • The plant has a capacity of 2,120 metric tons of ammonia per day.
  • The project delivers an annual IRR on investment of over 25%.
  • The unit was installed while the plant was in full operation.

Project Overview

thyssenkrupp Uhde has completed the start-up of a hydrogen recovery unit (HRU) at Fertiglobe's Fertil plant in Ruwais, UAE. The project involved engineering, procurement, and site supervision during installation and start-up.

Ammonia Production and Efficiency

Post-revamp, the plant now operates with a capacity of 2,120 metric tons of ammonia per day. The HRU enhances hydrogen recovery from ammonia synthesis purge gas, increasing feedstock utilization and boosting ammonia output by 6%.

Environmental Impact

This project marks a significant step towards sustainable ammonia production, reducing carbon dioxide emissions per ton of ammonia produced. The HRU and an extended ammonia recovery unit were installed without interrupting ongoing operations.

Financial and Operational Benefits

The project delivers an annual internal rate of return (IRR) on investment of over 25%, aligning with Fertiglobe's Manufacturing Improvement Plan focused on production and energy efficiency.

Source: thyssenkrupp Uhde

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

11 September 2026
Covestro, Fertiglobe and MB Energy explore ammonia supply chain via proposed Hamburg terminal

MoU to evaluate ammonia imports through a proposed Blumensand (Hamburg) terminal, offtake for feedstock/hydrogen, and transport links to industrial customers across Europe.

18 August 2026
thyssenkrupp Carbon2Chem® marks ten years as a blueprint for climate‑neutral industry

Transforms blast‑furnace CO₂ and renewable hydrogen into chemicals and fuels; moving from Duisburg demonstration to industrial scale and a SAF plant.

12 February 2026
thyssenkrupp Q1 2025/2026: Sales Down, EBIT Up, Forecast Confirmed

Order intake fell due to prior major contracts. Sales dropped 8%, but EBIT rose 10% via APEX program. Transformation progresses with strategic moves in various segments.

28 September 2026
OCI Global H1 2026 results and strategic progress

Net profit USD 1m; sold ammonia distribution and monetized Methanex; OCI Nitrogen impaired and facing margin pressure; held‑for‑sale net cash USD 1.05bn; NNS offer and Orascom deal progressing.

1 July 2026
OCI recommends NNS EUR 4.10 all-cash offer; court-appointed directors consent to convene EGM for Orascom vote

Board (excluding Nassef and Nadia Sawiris) backs NNS cash offer and court-appointed directors agree to convene an EGM to approve the Orascom transaction, conditional on NNS declaring and settling the offer.