CNPC Tarim Phase II 1.2 Mt/yr green low‑carbon ethylene project enters commercial operation

Key highlights
  • Project entered full commercial operation on October 15 after startup on July 16.
  • Phase II capacity is 1.2 million t/yr, establishing a 3 million t/yr ethylene cluster in Xinjiang.
  • Since startup the unit produced >260,000 t ethylene and supplied 566,000 t of chemical products with a 100% qualification rate.
  • The project has captured and utilized >100,000 t CO2 and produced >120,000 t of green urea using flue‑gas CO2 recycling.
Related project For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
PetroChina Tarim 1.2 Mt/yr phase II ethylene project · China
Operational / Completed
2023
2023-09
2023-11
2026-05-21
2026-10-15

Commercial operation and output

The Tarim 1.2 million‑metric‑ton‑per‑year Phase II ethylene project entered full commercial operation on October 15 after successful startup on July 16. Since commissioning it has produced more than 260,000 metric tons of ethylene and supplied 566,000 metric tons of high‑quality chemical products with a 100% qualification rate; polypropylene and MTBE products have been exported to Central Asian markets.

Decarbonisation and circular technologies

The facility implements a full‑chain closed‑loop low‑carbon technology system that integrates green electricity direct connection, carbon capture, blue hydrogen, blue ammonia and green fertilizers. It features China’s first ethylene three‑machine electric drive unit using proprietary technology and the world’s first demonstration base that recycles CO2 from ethylene cracking furnace flue gas to produce urea. To date the project has captured and utilized more than 100,000 metric tons of CO2 and produced over 120,000 metric tons of green urea.

Localization and industry impact

Ten of the project’s 11 major production units adopt domestically developed technologies, nine of them using CNPC proprietary technology, giving an overall localization rate of 99%. The Phase II start raises CNPC’s ethylene cluster in Xinjiang to long‑term stable operation at about 3 million t/yr and increases CNPC’s total ethylene capacity to more than 12 million t/yr, helping address uneven regional distribution and strengthen industrial‑chain resilience.

Source: PetroChina

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

19 August 2026
CNPC's 800 MW wind-solar project in Jimunai begins grid supply

600 MW wind and 200 MW PV with 80×7.5 MW turbines and a 220 kV substation, targeting 1.6 billion kWh/year and cutting 0.96 Mt CO2 annually.

29 September 2026
CNPC-led ISO issues first international EOR standard

ISO issues the first global standard defining EOR terms and definitions, covering chemical, gas, thermal and microbial recovery methods.

25 August 2026
MAIRE awards ~€50m in STS contracts to Nextchem/Stamicarbon

Contracts fund urea licensing, PDP and proprietary equipment across Asia, Europe and North America, plus a feasibility study for a 40,000 t/yr polyolefin upcycling plant.

29 July 2026
SABIC Q2 2026 revenue $6.62bn; earnings fall

Q2 sales fell 5% Q-o-Q; adjusted EBITDA SAR 3.38bn; H1 dividend SAR 3.3bn; Fujian complex start-up expected Q4 2026.

21 May 2026
PETRONAS Chemicals Group 1Q2026: 97% plant utilisation and improved earnings

High plant utilisation, RM7.0bn revenue and RM1.2bn EBITDA; PAT RM427m vs LAT RM730m prior quarter amid higher commodity prices.