EnviTec Biogas advances Vara biomethane and bio‑LNG plant construction
- The EnviThan gas upgrading system passed the Factory Acceptance Test and has been assembled on site.
- Cold commissioning of the plant is planned for autumn, with biological filling and start-up to follow under EnviTec supervision.
- First biomethane production is scheduled for January 2027.
- The facility is designed for about 370,000 tonnes/year of input and up to 70 GWh of biomethane annually.
Construction progress and commissioning
One year after the first ground‑breaking, construction of the combined biogas and gas upgrading plant in Vara is progressing as planned. The EnviThan gas upgrading plant passed the Factory Acceptance Test and has been assembled on site. Feeding technology, concrete tanks (built by EnviTec‑Greten) with interior fit‑out, the first air‑supported roofs and a heat exchanger have been delivered and installed. Piping, electrical and further mechanical installation work are ongoing, creating the prerequisites for the cold commissioning planned for the autumn.
Feedstock, process flow and biological start‑up
Tanks will be filled with substrate sourced from surrounding biogas plants; liquid substrate will be unloaded in a dedicated technical building, pumped to the intake tank and routed to the fermenters. Solid substrate will be added via the installed feeding technology and mixed with the liquid fraction to ensure even substrate supply and stable biogas production. EnviTec will support the filling process with biological supervision and a defined start‑up and ramp‑up plan.
Upgrading, capacity, design and schedule
Produced biogas will be upgraded to biomethane using the EnviThan membrane process, adjusted for the downstream liquefaction plant and transferred directly to the customer’s bio‑LNG production. The industrial‑scale plant, run by a cooperative of around 100 farmers, will process pig and cattle slurry and regional manure, handling about 370,000 tonnes of input per year and delivering up to 70 GWh of biomethane annually. Enclosures and equipment are designed for Swedish snow and wind loads, a publicly appointed expert inspects construction phases, and first biomethane production is scheduled for January 2027.
Source: EnviTec Biogas