Aurora Renewable Carbon secures financing to restart Empyro plant

Key highlights
  • Financing package from Triodos Bank, Oost NL (via ION+3 Fund/ERDF), a group of angel investors and Aurora management secured the restart.
  • Empyro will resume production of pyrolysis bio-oil from woody biomass residues later this summer, initially supplying existing industrial customers.
  • The plant produced pyrolysis bio-oil since 2015 but halted operations in early 2023; Aurora has taken over operation.
  • Aurora plans an on-site upgrading facility to separate lignin and sugars and refine them into customer-specific biobased feedstocks for resins, coatings, composites and other specialty chemicals.
Related projects For subscribers
Milestones, plant data, involved companies (owners, investors, licensors, contractors) and news — kept up to date.
Aurora Renewable Carbon Empyro Bio-Oil Restart Hengelo · The Netherlands
Operational / Completed
2025-10
2026-07-23
~2026-08
2026-10-09
Aurora Renewable Carbon Empyro Restart and Biorefinery Twente · The Netherlands
Operational / Completed
2026-07-23
2026-07-23
2026-10-09

Financing and partners

Aurora Renewable Carbon obtained financing from a consortium including Triodos Bank, Oost NL, a group of angel investors and the company’s management. Oost NL is investing through the ION+3 Fund, which is co-financed by the European Regional Development Fund (ERDF).

Plant restart

The Empyro plant in Hengelo, which produced pyrolysis bio-oil from woody biomass residues since 2015 and halted production in early 2023, will restart later this summer under Aurora’s operation. Production will initially serve existing industrial customers.

Upgrading and product slate

Aurora will expand the facility with an upgrading plant that separates lignin and sugars from pyrolysis bio-oil and refines them to customer-specific quality standards. The resulting biobased feedstocks are intended for resins used in insulation materials, coatings, composite materials and other specialty chemicals.

Strategic context

The project is presented as the foundation for an integrated wood pyrolysis-based biorefinery at a single Hengelo site, aiming to transform woody biomass residues into higher-value materials, support a circular chemicals value chain and contribute to decarbonisation. The plan builds on an earlier ERDF-supported project that developed the underlying technology and applications.

Source: Aurora Renewable Carbon

chemXplore Weekly

The week’s project milestones and project news from the chemical industry, free every Wednesday.

Free. One email a week. Unsubscribe any time.

Related articles

9 October 2026
Aurora delivers first pyrolysis bio-oil from Empyro

First load of pyrolysis bio-oil delivered to FrieslandCampina for co-firing in industrial steam boilers, partially replacing natural gas.

21 May 2026
Aurora Renewable Carbon and Ten Damme agree long-term biomass supply for Empyro

Long-term deal secures sustainably sourced wood residues for Empyro bio-oil plant restart; feedstock will meet NTA 8080 traceability and sustainability criteria.